Reference · The institutions
The Public Utility Commission and Bitcoin: The List It Keeps
Every megawatt a Bitcoin mine draws in Texas runs through a grid operator the Legislature rebuilt after the 2021 freeze and a five-member commission that writes the operator's rules. The commission did not meet the mines first – ERCOT did, in March 2022, with an interim process it called temporary and never replaced. What the commission has done on its own is a short list. It took seventeen months to write the registry the Legislature ordered in 2023, made the registry heavier than the statute, and then sued the Attorney General to keep the registrations secret. It has spent 2026 writing the rules for a load that grew seven-fold while it wrote them – four hundred and seventy-four gigawatts asking to connect to a grid whose record peak is ninety-one – and in July it asked the Legislature to make every data center register too. The registry, the suit, the rule board, and the queue are the record.
By TexasBitcoin · Published September 25, 2026 · Updated September 25, 2026
The short answer
The Public Utility Commission of Texas is the five-member, governor-appointed regulator that oversees ERCOT and writes the rules the state's grid statutes require. On Bitcoin its own record is the mining registry – 16 TAC § 25.114, adopted November 21, 2024 under SB 1929 – the June 27, 2025 lawsuit against the Attorney General to keep those registrations secret, and the 2026 rules under SB 6: forecasting and co-location adopted, interconnection standards still proposed, a 12CP replacement for the 4CP transmission charge due in December, Batch Zero approved in June and paused in August for an audit that includes every crypto facility over 25 megawatts.
Key facts
- The commission adopted the SB 1929 mining registration rule, 16 TAC § 25.114, on November 21, 2024, with penalties up to $25,000 per violation per day.[12][11]
- On June 27, 2025 the commission sued the Attorney General to block release of the registrations after a May 15, 2025 ruling ordered them disclosed.[15][16]
- ERCOT, not the commission, created the interim large-load process on March 25, 2022 and the voluntary curtailment program for “bitcoin mining facilities” on December 6, 2022.[4][6]
- Under SB 6 the commission adopted the forecasting rule (effective March 1, 2026) and the co-location rule (March 26, 2026); the interconnection standards proposed March 12, 2026 remain pending.[20][22][21]
- Commission staff's March 2026 report named “crypto mines and certain types of data centers” as loads that avoid transmission costs “without commensurate system cost reductions.”[24]
- On August 20, 2026 the commission paused Batch Zero for an audit of 250 to 300 projects, including crypto facilities of 25 MW or more, after the Governor cited a 474-gigawatt queue.[30][32]
From the freeze to the audit
2021 → 2026- The commission
Three seats become five, and a new chair after the storm
Winter Storm Uri empties the commission; Governor Abbott names Peter Lake chair on April 12, 2021, and in June signs SB 2154, expanding the commission from three members to five, requiring them to live in Texas, and barring them from lobbying for a year after leaving. Its executive director since December 2020 is Thomas Gleeson, fifteen years at the agency. The commission that will meet the mines is the one Uri made. [1][2][3]
- The mines
ERCOT meets the mines: the interim process, the task force, the program
The grid operator, not the commission, moves first. On March 25, 2022 ERCOT issues an interim interconnection process for loads of 75 megawatts or more - effective immediately, no crypto in the text, crypto the plain occasion. A Large Flexible Load Task Force meets from April 14; on December 6 ERCOT opens a voluntary curtailment program for "large flexible customers, such as bitcoin mining facilities," temporary until permanent rules that never come. In Winter Storm Elliott that month the mines cut from 1,530 to 130 megawatts at the peak. [4][5][6][7]
- The mines
The Legislature writes the registry; the commission registers "on"
At the March 28, 2023 hearing on Kolkhorst's SB 1751 and Johnson's SB 1929, Gleeson registers "on" - a resource, not a position - while Riot and US Bitcoin testify against the brake and the Sierra Club for it. The brake dies in the House; the registry passes and takes effect September 1: any mining facility over 75 megawatts registers with the commission within one business day of its power deal, with a five-year forecast. That August Riot collects $31.7 million for standing down - $7.4 million of it from ERCOT's ancillary services, the rest from its power contract. [10][9][8]
- The list
Seventeen months to a rule: 16 TAC § 25.114
The commission adopts the registration rule on November 21, 2024, fourteen months after the statute took effect and heavier than the bill: location, owners, business form, demand, a five-year peak forecast, prior-year consumption, annual renewal, existing sites registered by February 1, 2025, penalties up to $25,000 per violation per day, and the data collected in a tool the public cannot see. Gleeson: "the PUCT and ERCOT need to know the location and power needs of virtual currency miners." Bratcher, for the industry: "appropriate and far less invasive than what the Federal Government attempted." Roughly 2,600 megawatts of mining is on the grid, with as much again approved. That February, Commissioner Glotfelty compares the miners' grid-hero story to teenagers praised for fighting a grass fire their own fireworks started. [11][12][13][36]
- The list
The list, requested, ordered released, and defended in court
Reporters for Straight Arrow News and the Texas Tribune ask for the registrations. The commission refuses under the critical-infrastructure exception. On May 15, 2025 the Attorney General's office rules the commission "failed to demonstrate" the data identifies particular vulnerabilities and orders it released. On June 27 the commission sues the Attorney General: "In the wrong hands, this information could be used by terrorists to plan attacks on Texas's energy grid and critical infrastructure." By November it has spent about $13,000 on the case; no ruling has been reported. How many sites registered has never been disclosed. [15][16][17]
- The load
SB 6 hands the commission the load
The large-load law takes effect: a 75-megawatt threshold the commission may lower, a $100,000 minimum study fee, site control and disclosure of backup generation, mandatory curtailment for loads interconnecting after December 31, 2025, ERCOT's emergency authority, and an order to the commission to re-examine how transmission costs are allocated - the 4CP method the mines have learned to play - by December 31, 2026. Staff maps it into five projects: 58480 forecasting, 58481 interconnection, 58479 co-location, 58482 demand management, 58484 the 4CP study. The queue in the October deck: 189 gigawatts, 69% data centers. [18][19]
- The load
Two rules adopted, one proposed, and a staff report that names the mines
The forecasting rule, § 25.370, takes effect March 1. The co-location rule, § 25.205, is adopted March 26: no net-metering arrangement behind an existing plant without commission approval after ERCOT's 120-day study and a 60-day decision. The interconnection standards, § 25.194, are proposed March 12 - $50,000 per megawatt in security, $100,000 to $300,000 study fees, 80% forfeiture on withdrawal - and remain unadopted in September. And staff's draft 4CP report names "crypto mines and certain types of data centers" as loads that avoid transmission costs "without commensurate system cost reductions." ERCOT counts 410 gigawatts in the queue on April 9, 87% of it data centers. [20][22][21][24]
- The load
Batch Zero, the Governor's letter, and 12CP
On June 10 the Governor orders the commission to make data centers pay their full infrastructure costs and lower residential bills. On June 18 it approves ERCOT's batch study process - every six months, all requests studied together, 438 gigawatts in the queue. On July 9 it publishes staff's replacement for 4CP: twelve coincident peaks on thirty-minute intervals, a minimum billing demand, and ERCOT access to large-load meters, with staff modeling the residential share of transmission cost down three points; decision due in December. On July 17 the commission and ERCOT ask the Legislature for emergency communication with data centers and mandatory registration of all of them. Gleeson: "A Bitcoin miner is different from a hyperscaler, is different from a steel mill or a chemical plant." [29][28][25][31][26]
- The watch
The audit, the ride-through rule, the 765-kV vote
On August 3 the Governor cites "approximately 474 gigawatts ... more than five times Texas' record peak" and orders an audit of every data center in the queue before any more are approved. On August 20 the commission grants ERCOT's request to pause Batch Zero classification; the audit covers 250 to 300 projects and every crypto facility of 25 megawatts or more. In July it had adopted, unanimously, a ride-through rule requiring large computational loads to stay connected through grid disturbances - 28 trips of 100 megawatts or more since 2023 - over the Blockchain Council's objection to battery costs. On August 28 it approves the first 765-kV lines of the Permian plan, unanimously, over 43 legislators' amicus and Ken King's letter. Hjaltman, to the landowners: "They're about your land." [30][32][33][34]
What is the commission, and what is ERCOT?
Two bodies the press calls one. The Public Utility Commission of Texas is the regulator: created by the Public Utility Regulatory Act in 1975, three members until the Legislature made it five in SB 2154 after Winter Storm Uri, each appointed by the governor, required since 2021 to live in Texas and to stay out of lobbying for a year after leaving.[1] It writes rules in the Texas Administrative Code, approves or rejects the grid operator's protocol changes, decides contested cases, and answers to the Legislature and the Governor. Peter Lake chaired it from April 2021 until July 2023; Thomas Gleeson, its executive director since December 2020 and fifteen years at the agency, has chaired it since January 23, 2024.[2][3] ERCOT is the grid operator the commission oversees: the nonprofit that runs the market, the interconnection queue, the ancillary services, and the curtailment programs, under a board the same 2021 session rebuilt. When a Bitcoin mine sells its load back to the grid, it sells to ERCOT under ERCOT's rules; when the state decides what a large load must do to connect, the commission writes the rule and ERCOT applies it. This page keeps them apart, because on the mines the operator moved first and the commission followed. The senator who wrote the commission's large-load statute is on Phil King and Bitcoin; the sites the rules govern are on the Texas Bitcoin mining map.
How did the grid meet the mines?
Through ERCOT, in 2022, with instruments the operator called temporary. On March 25, 2022 ERCOT issued an interim interconnection process for standalone loads of 75 megawatts or more and co-located loads of 20, effective immediately – a market notice that never says the word crypto and was written for nothing else.[4] A Large Flexible Load Task Force met from April 14, was chartered in May, and is now inactive, succeeded by a working group.[5] On December 6, 2022 ERCOT opened a voluntary curtailment program for “large flexible customers, such as bitcoin mining facilities,” to run “until ERCOT establishes a long-term set of rules.”[6] Two weeks later Winter Storm Elliott arrived, and ERCOT's report recorded the mines doing what the industry says they do: the large flexible loads “curtailed their consumption from 1,530 MW to 130 MW (a 91.5% reduction) during the peak,” all twenty known sites, most of them once prices passed $70 to $110 a megawatt-hour.[7] In August 2023 Riot Platforms reported $31.7 million for standing down at Rockdale – $7.4 million of it ERCOT's ancillary-service payments, $24.2 million power credits under its contract with TXU – and the number became the industry's argument and its critics' in the same week.[8] The commission's role in all of it was oversight: no rule of its own, no statement on the mines in Elliott or in the August heat that has been located, and when the Legislature took up the question in March 2023, its executive director registered “on” – a resource for the committee, not a witness for either side – while Riot and US Bitcoin testified against Kolkhorst's brake and the Sierra Club for it.[10] The brake is on Lois Kolkhorst and Bitcoin; the Rockdale site is on Rockdale, Texas and Bitcoin.
What is the registry, and why did it take seventeen months?
The one rule the commission wrote for the mines alone. SB 1929, Nathan Johnson's 2023 statute, requires any virtual-currency mining facility in ERCOT expecting more than 75 megawatts to register with the commission within one business day of its power agreement, with a five-year demand forecast, and lets the commission share the data with ERCOT.[9] It took effect September 1, 2023. The commission opened Project 56962, published a proposed rule in September 2024, and adopted 16 TAC § 25.114 on November 21, 2024 – fourteen months after the statute, seventeen after it was signed – and made it heavier than the bill: location, owners, business form, electricity demand, a five-year peak forecast, prior-year consumption, annual renewal, existing facilities registered by February 1, 2025, and a Class A violation of up to $25,000 per day for failing to, all collected through an internal tool the public cannot see.[11][12] Gleeson: “To ensure the ERCOT grid is reliable and meets the electricity needs of all Texans, the PUCT and ERCOT need to know the location and power needs of virtual currency miners.” Lee Bratcher, for the Blockchain Council: “The information that the PUC is requesting is appropriate and far less invasive than what the Federal Government attempted under the Biden Administration earlier this year.”[13] About 2,600 megawatts of mining was on the grid at adoption, with as much again approved; by 2025 the mines drew some 54 billion kilowatt-hours, roughly a tenth of ERCOT's consumption.[12][14] The commission has never said how many facilities registered. The senator who wrote the statute, and waited for the rule, is on Nathan Johnson and Bitcoin.
Why did it sue the Attorney General?
To keep the list. Reporters for Straight Arrow News and the Texas Tribune requested the registrations – names, locations, owners, megawatts, demand-response enrollment. The commission refused, citing the Public Information Act's exception for critical infrastructure, and asked the Attorney General to agree. On May 15, 2025 an assistant attorney general ruled the commission “failed to demonstrate the information at issue identifies the technical details of particular vulnerabilities of critical infrastructure to an act of terrorism” and ordered release.[15] On June 27, 2025 the commission sued the Attorney General: “In the wrong hands, this information could be used by terrorists to plan attacks on Texas's energy grid and critical infrastructure” through “manipulation of the volume of available reliable electricity.” Its press officer declined to comment on pending litigation; Riot and Marathon declined to comment at all.[16] By November it had spent about $13,000 of the $56,000 in outside counsel it paid that year fighting three records rulings, and the case was still pending; no ruling has been reported since.[17] Two things sit beside the suit. In July 2026 the same commission asked the Legislature for mandatory registration of every data center and large load – more of the data it is litigating to keep – and in August its audit swept in every crypto facility of 25 megawatts or more, a third of the registry's threshold.[31][32]The office it sued, and the ruling it is fighting, are on the Texas Attorney General and Bitcoin.
What has it written under SB 6?
Two rules, two proposals, and a replacement for the charge the mines learned to dodge. The large-load law of June 20, 2025 set a 75-megawatt threshold the commission may lower, a $100,000 minimum study fee, site control, disclosure of backup generation, mandatory curtailment for loads interconnecting after December 31, 2025, ERCOT's emergency authority, and a deadline of December 31, 2026 for the commission to re-examine how transmission costs are allocated.[18] Staff mapped it into five projects that October, with the queue at 189 gigawatts and a line that would matter: “Diverse types of large loads may warrant different treatment.”[19]The forecasting rule, § 25.370, took effect March 1, 2026: after this year only loads with a compliant interconnection agreement count in ERCOT's forecast.[20] The co-location rule, § 25.205, was adopted March 26: no net-metering arrangement behind an existing generator without the commission's approval after ERCOT's 120-day study and a 60-day decision, and the first case – Crusoe's 260-megawatt AI data center at a wind farm in Hutto – was approved July 23 on condition of full curtailment within thirty minutes of ERCOT's direction, breaker disconnection authorized, no compensation.[22][23] The interconnection standards, § 25.194, were proposed March 12 – $50,000 per megawatt in security, study fees of $100,000 to $300,000, an 80% forfeiture on withdrawal – and had not been adopted in September; the demand-management service, which by its terms excludes loads already selling flexibility, is pending too.[21][22] The 4CP review became something larger. Staff's March draft named “crypto mines and certain types of data centers” as flexible loads that cut consumption at the four summer peaks “without commensurate system cost reductions”; on July 9 the commission published staff's replacement – twelve coincident peaks on thirty-minute intervals, a minimum billing demand, ERCOT access to large-load meters – modeled to move three points of transmission cost off residential customers, with a decision targeted for December.[24][25] The chairman's formulation, in June: “A Bitcoin miner is different from a hyperscaler, is different from a steel mill or a chemical plant.” “The megawatt we don't use is just as important as the megawatt that we generate.”[26] The House chairman who reshaped the law the rules implement is on Ken King and Bitcoin.
What happened to the queue?
It outran the rules. Large loads seeking interconnection stood at 63 gigawatts at the end of 2024; 189 in the commission's October 2025 deck; 233 at the end of 2025 – “We have outgrown the process,” ERCOT's Kristi Hobbs said in January – 410 when ERCOT briefed the House on April 9, 2026, 87% of it data centers; 438 when the commission approved ERCOT's Batch Zero process on June 18, under which every request is studied with every other every six months.[35][19][20][28] On June 10 the Governor had written Gleeson and ERCOT's Pablo Vegas to make data centers pay “all of their electric infrastructure costs” and to see that their interconnections “result in reduced residential electrical bills”; on July 17 the commission and ERCOT answered with a joint memo asking the Legislature for direct emergency communication with data centers and mandatory registration of all of them – “Texas should welcome responsible economic development,” Gleeson said, “but it must do so in a manner that prioritizes affordability, reliability, and the interests of the residents who depend on the grid.”[29][31] On August 3 the Governor cited “approximately 474 gigawatts … more than five times Texas' record peak” and ordered a “comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process before any additional data centers are approved.”[30] On August 20 the commission granted ERCOT's request to pause Batch Zero's classification; the audit covers 250 to 300 projects and, by ERCOT's notice, every crypto facility of 25 megawatts or more, with a filing targeted for December 10.[32] In between, the commission adopted unanimously a ride-through rule requiring large computational loads to stay connected through voltage and frequency disturbances – 28 trips of 100 megawatts or more since 2023 – over the Blockchain Council's objection that battery mitigation would cost “more than $1.6 million per MW,” and on August 28 approved the first 765-kilovolt lines of the Permian Basin plan over the objection of 43 legislators and Ken King's letter, Commissioner Hjaltman telling the landowners, “I understand the proceedings are not just about infrastructure to you. They're about your land.”[33][34] The governor who wrote both letters is on Greg Abbott and Bitcoin.
The honest counterweight: the slowness, the loophole, and the secrecy
Three things, and the commission's own documents supply two of them. First, slowness. ERCOT's 2022 process was interim and its program “temporary”; the task force went inactive without a permanent large-flexible-load rule; the durable framework arrived only with a statute in 2025 and a batching process in 2026, by which time the operator's own vice president said it had outgrown the process.[6][5][35] The registry took seventeen months; the interconnection standards, proposed in March, are the rule the industry files under and the one still open.[12][21] Second, the loophole, in staff's words: the four-coincident-peak charge let “crypto mines and certain types of data centers” shed load at the peaks and avoid transmission costs “without commensurate system cost reductions,” and the commission is only now, under statutory deadline and gubernatorial letter, replacing it – a decade after the mines arrived and a year and a half after Commissioner Glotfelty likened their grid-hero reputation to teenagers praised for putting out a grass fire their fireworks had started.[24][36] Third, secrecy. An agency that wants the Legislature to make every data center register, and that is auditing every mine over 25 megawatts, is in court to keep the public from seeing which mines over 75 registered, on a terrorism theory the Attorney General found unproven; the two positions can be reconciled – the agency wants the data, not the public to have it – but the reconciliation is the point.[16][31] What cuts the other way is real. The mines did cut 91.5% at Elliott's peak; the ride-through rule and the co-location conditions put the reliability risk on the load, as the chairman says, “on the private company, not on the citizens”; and the industry itself has called the registry “appropriate” and the large-load law a fix for the “phantom load.”[7][26][13][18]
The fair reading is that the commission has treated Bitcoin mining as a load problem and not a policy one – it has never said the mines should or should not be in Texas, only that it needs to know where they are and that they should pay their share of the wires – and that both of those positions were reached late and are still being written into rule. The question the commission has not answered, and the one its audit will force, is whether a miner that sells its flexibility is a benefit the grid should pay for or a cost it should recover, and its staff and its chairman have now said both.
Where does the commission stand today?
As of September 2026: two SB 6 rules adopted and two pending, a 12CP decision due in December, Batch Zero paused for an audit due December 10, a records suit against the Attorney General with no ruling, a registry whose count it has not disclosed, and a chairman with a term to 2029.[21][25][32][17][3] The 90th Legislature convenes January 12, 2027 with the commission's own request for data-center registration on its desk and the House chairman who will hear it on Ken King and Bitcoin. The regulator next door, which has never taken a position on the asset, is on the Texas Attorney General and Bitcoin; the statute-by-statute record the commission implements is on the Texas Bitcoin law timeline. This page is the list the commission keeps, and will not show.
Frequently asked questions
What is the Public Utility Commission of Texas, and how is it different from ERCOT?
The commission is the state regulator: five members appointed by the governor - three until SB 2154 in 2021 - who write rules under the Public Utility Regulatory Act, approve ERCOT's protocols, and answer to the Legislature and the Governor. Thomas Gleeson, its executive director from December 2020, has chaired it since January 2024. ERCOT is the grid operator the commission oversees: it runs the market, the interconnection queue, and the curtailment programs. In the Bitcoin record ERCOT moved first, in 2022; the commission's own actions are the 2024 registration rule, the 2025 records suit, and the SB 6 rules of 2026.
What is the Texas Bitcoin mining registry?
SB 1929, Nathan Johnson's 2023 law, requires any virtual-currency mining facility in ERCOT expecting more than 75 megawatts to register with the commission within one business day of its power agreement, with a five-year demand forecast. The commission adopted the implementing rule, 16 TAC § 25.114, on November 21, 2024 - fourteen months after the statute took effect - requiring location, ownership, demand, and consumption, with annual renewal and penalties up to $25,000 per violation per day. Existing facilities had to register by February 1, 2025. The commission has never said how many did.
Why did the commission sue the Attorney General?
To keep the registry secret. Reporters requested the SB 1929 registrations; the commission refused under the critical-infrastructure exception; on May 15, 2025 the Attorney General's office ruled the commission had not shown the data revealed particular vulnerabilities and ordered it released. On June 27, 2025 the commission sued, arguing that 'in the wrong hands, this information could be used by terrorists to plan attacks on Texas's energy grid.' It had spent about $13,000 on the case by November 2025. No ruling has been reported.
What has the commission done under SB 6?
Mapped the 2025 large-load law into five projects. Adopted: the forecasting rule (§ 25.370, effective March 1, 2026) and the co-location rule (§ 25.205, March 26, 2026 - ERCOT studies 120 days, the commission decides in 60; the first case, an AI data center at a Hutto wind farm, was approved in July with full curtailment within 30 minutes on ERCOT's direction). Proposed and pending: the interconnection standards (§ 25.194, published March 12, 2026 - $50,000 per megawatt in security, $100,000 to $300,000 study fees) and the demand-management service. The 4CP transmission-cost review became a proposal to move to twelve coincident peaks, published July 9, 2026, with a decision targeted for December. It also approved ERCOT's Batch Zero process on June 18, 2026 and the ride-through rule in July.
Does the commission think Bitcoin mines help or hurt the grid?
It has said both things in different documents. ERCOT's report on Winter Storm Elliott recorded the mines cutting 91.5% of their load at the peak, and Chairman Gleeson has said 'the megawatt we don't use is just as important as the megawatt that we generate' and that 'a Bitcoin miner is different from a hyperscaler.' The commission's own staff report of March 2026 named 'crypto mines and certain types of data centers' as loads that avoid transmission costs 'without commensurate system cost reductions,' which is the basis of the 12CP proposal. Commissioner Glotfelty in 2024 compared the miners' grid-hero story to teenagers praised for fighting a fire their fireworks started.
Sources
Primary record first: the commission's proposed rules, project filings, and staff deck; ERCOT's market notices, reports, and releases; the Governor's directive letters; the Legislature's bill analyses and witness lists; Riot's SEC filing; the Energy Information Administration; then Utility Dive, the Texas Tribune, Straight Arrow News, Inside Climate News, and Texas Monthly for the quotes, the suit, and the counterweight. The commission's own press-release server refused automated requests, so its releases are cited as reported. This is a research and reference article, not financial, investment, or legal advice.
- [1]Houston Chronicle - Texas PUC grows from three commissioners to five (2021): SB 2154 (87R), signed June 2021; Texas residency; a one-year lobbying ban
- [2]Texas Tribune - Texas power grid regulator chair Peter Lake to resign (June 2, 2023): appointed April 12, 2021; "our grid is more reliable than ever"
- [3]Office of the Governor - Governor Abbott appoints and names Gleeson chair of the Public Utility Commission of Texas (January 19, 2024): executive director since December 2020; term to September 1, 2029
- [4]ERCOT - Market notice W-A032522-01 (March 25, 2022): the interim large-load interconnection process - standalone loads of 75 MW or more, co-located loads of 20 MW or more, effective immediately
- [5]ERCOT - Large Flexible Load Task Force (inactive): first meeting April 14, 2022; charter approved May 25, 2022; succeeded by the Large Load Working Group
- [6]ERCOT - ERCOT creates voluntary curtailment program for large flexible loads (December 6, 2022): "large flexible customers, such as bitcoin mining facilities"; temporary until permanent rules
- [7]ERCOT - December 2022 cold-weather operations public report (March 27, 2023): large flexible loads curtailed from 1,530 MW to 130 MW, a 91.5% reduction, during Winter Storm Elliott's peak
- [8]Riot Platforms - Form 8-K exhibit (September 6, 2023): August 2023 - about $7.4 million in ERCOT ancillary services and $24.2 million in power credits under the TXU contract, $31.7 million total
- [9]Texas Legislature Online - SB 1929 (88R) enrolled bill analysis: virtual-currency mining facilities over 75 MW register with the commission within one business day; five-year demand forecast; effective September 1, 2023
- [10]Texas Legislature Online - SB 1751 (88R) Senate witness list, March 28, 2023: Thomas Gleeson, PUC executive director, registered "On" as a resource; Riot and US Bitcoin against; Sierra Club and Public Citizen for
- [11]Public Utility Commission of Texas - Project 56962, proposal for publication of 16 TAC § 25.114, registration of virtual-currency mining facilities (September 2024, PDF)
- [12]Texas Tribune - Texas will require cryptocurrency miners to register with the state's grid regulator (November 25, 2024): adopted November 21, 2024; register by February 1, 2025; up to $25,000 per violation per day; about 2,600 MW of mining load with as much again approved
- [13]Utility Dive - Texas requires bitcoin miners to register with grid operator ERCOT (November 2024): Gleeson - "the PUCT and ERCOT need to know the location and power needs of virtual currency miners"; Bratcher - "appropriate and far less invasive than what the Federal Government attempted"
- [14]U.S. Energy Information Administration - Today in Energy: Texas cryptocurrency mining consumed about 54 billion kWh in 2025, roughly 10% of ERCOT consumption
- [15]Straight Arrow News - SAN reporter's inquiry into Texas bitcoin mines triggers lawsuit (August 7, 2025): the records requests; the Attorney General's May 15, 2025 ruling; the commission's June 27 suit
- [16]Texas Tribune - Texas utility regulators sue attorney general to keep crypto-mining power data secret (August 11, 2025): "In the wrong hands, this information could be used by terrorists to plan attacks on Texas's energy grid"
- [17]Straight Arrow News - Texas utility commission spent $56K blocking public-records release (November 10, 2025): about $13,000 on the crypto case; still pending
- [18]Utility Dive - Texas law gives grid operator power to disconnect data centers during crisis (June 25, 2025): SB 6 signed June 20; the 75 MW threshold, the $100,000 study fee, curtailment for loads after December 31, 2025, the 4CP review by December 31, 2026; Bratcher on the "phantom load"
- [19]Public Utility Commission of Texas via NASEO - SB 6 implementation staff deck (October 17, 2025, PDF): Projects 58480 forecasting, 58481 interconnection, 58479 net metering, 58482 demand management, 58484 4CP; queue 189 GW, 69% data centers; "Diverse types of large loads may warrant different treatment"
- [20]ERCOT - Large Load Update, House State Affairs hearing (April 9, 2026, PDF): about 410 GW tracked, about 87% data centers; § 25.370 forecasting rule effective March 1, 2026; batch studies every six months
- [21]Public Utility Commission of Texas - Project 58481, proposal for publication of 16 TAC § 25.194, large-load interconnection standards (March 12, 2026, PDF): $50,000 per MW security, $100,000 to $300,000 study fees, site control, 80% forfeiture on withdrawal
- [22]Perkins Coie - SB 6 implementation: shaping the data-center future in Texas (2026): § 25.205 co-location rule adopted March 26, 2026 - ERCOT 120-day study, commission 60-day decision; 58482 demand-management service pending
- [23]Utility Dive - Texas approves AI data center co-location next to wind farm, with curtailment (July 24, 2026): the first § 25.205 case, Crusoe at Hutto - full curtailment within 30 minutes on ERCOT's direction, breaker disconnection authorized
- [24]K&L Gates - Request for comments on the PUCT draft report on transmission cost recovery in ERCOT (March 30, 2026): staff names "crypto mines and certain types of data centers" as flexible loads that cut peak demand "without commensurate system cost reductions"
- [25]Public Utility Commission of Texas - Project 58000, staff proposal on transmission cost allocation (June 2026, PDF): 12CP on 30-minute intervals, minimum billing demand, ERCOT access to large-load meter data; residential share modeled down 3.1 points
- [26]Texas Energy & Power - The regulator's test for real load (June 10, 2026): Gleeson - "A Bitcoin miner is different from a hyperscaler, is different from a steel mill or a chemical plant"; "The megawatt we don't use is just as important as the megawatt that we generate"
- [27]Inside Climate News - The chairman of Texas' Public Utility Commission has a to-do list (May 20, 2025): Gleeson - "We want this economic development here, but it needs to be done in a managed way that we are sure is not going to impair reliability"
- [28]ERCOT - PUCT approves ERCOT's new large-load interconnection process (June 18, 2026): NPRR1325 and PGRR145, Batch Zero; queue 438 GW, 89% data centers; Vegas - "a fundamental shift"
- [29]Office of the Governor - Directive letter to Chairman Gleeson and CEO Vegas (June 10, 2026, PDF): data centers to pay "all of their electric infrastructure costs" and interconnections to "result in reduced residential electrical bills"
- [30]Office of the Governor - Directive letter to Gleeson and Vegas (August 3, 2026, PDF): "approximately 474 gigawatts ... more than five times Texas' record peak"; "comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process before any additional data centers are approved"
- [31]Texas Tribune - Texas grid regulators ask lawmakers for more control over data centers (July 29, 2026): the July 17 joint memo - emergency communication, mandatory registration of data centers and large loads; Gleeson - "Texas should welcome responsible economic development, but it must do so in a manner that prioritizes affordability, reliability, and the interests of the residents who depend on the grid"
- [32]Utility Dive - ERCOT, Texas PUC launch data center audit (August 21, 2026): Project 59142 good-cause request granted August 20; roughly 250 to 300 projects; crypto facilities of 25 MW or more included; Gleeson - "more certainty and confidence in the Batch Zero process"
- [33]Utility Dive - Texas PUC approves ride-through rules for data centers (July 13, 2026): NOGRR282, unanimous; 28 large-load trips of 100 MW or more since 2023; the Texas Blockchain Council opposed battery mitigation at "more than $1.6 million per MW"
- [34]Texas Tribune - Texas approves first 765-kV transmission lines despite opposition (August 28, 2026): the Permian Basin plan's Oncor lines, unanimous; Hjaltman - "They're about your land"; the 43-lawmaker amicus
- [35]Utility Dive - ERCOT's large-load queue jumped almost 300% last year (January 6, 2026): 63 GW at the end of 2024 to 233 GW; Kristi Hobbs - "We have outgrown the process"
- [36]Texas Monthly - Texas crypto miners and the grid (February 28, 2024): Commissioner Jimmy Glotfelty's grass-fire analogy - the newspaper "called us heroes – without mentioning it was our fireworks that started the fire in the first place"; Riot's $71.2 million in 2023 credits