ERCOT and Bitcoin: The Load It Counts as a Resource

The grid operator for ninety percent of Texas has never had a policy on Bitcoin, and does not need one. It has a category. In its capacity report every load on the system is firm except one class, the large flexible load, which its glossary says “is typically a crypto-currency mining site”; in its storm reports that class is the one that gave back 91.5% of its power at the December 2022 peak and four thousand megawatts on a January weekend in 2026; in its reserve services it is all twelve of the loads registered as controllable and sixty-four percent of the capacity it buys for emergencies. The mines came to ERCOT because it would pay them to be flexible, and ERCOT planned around them because they were – and its own market monitor now says the paying was for behavior the price already bought. The load, the storms, the reserve, and the queue that buried the mines under data centers are the record.

By TexasBitcoin · Published September 26, 2026 · Updated September 26, 2026

The short answer

ERCOT, the nonprofit grid operator for about 90 percent of Texas, treats Bitcoin mines as large flexible loads – the one class of load its planning counts as non-firm – and lets them sell their ability to switch off into its reserve services. Its own reports record the mines cutting from 1,530 to 130 megawatts in Winter Storm Elliott and about 4,100 megawatts in Winter Storm Fern, put mining demand near 4,600 megawatts in 2025, and show crypto holding 64% of the emergency reserve service. Its Independent Market Monitor concluded in 2026 that paying mines for that service “essentially pays them to do what they would already do,” and ERCOT has proposed excluding price-responsive loads. Since 2024 the mines have been a shrinking share of a queue that grew from 63 to 474 gigawatts of mostly data centers.

Key facts

  • ERCOT's capacity report assumes all loads other than large flexible loads “(i.e., crypto-currency mining)” are firm.[26]
  • In Winter Storm Elliott, registered large flexible loads “curtailed their consumption from 1,530 MW to 130 MW (a 91.5% reduction)” at the peak.[14]
  • In Winter Storm Fern, January 2026, ERCOT reported “cryptocurrency mining began reducing ~4,100 MW.”[33]
  • All twelve Controllable Load Resources registered in 2025 were cryptocurrency mines, and crypto held more than 64% of emergency reserve capacity.[34][32]
  • Of Riot's $31.7 million in August 2023 credits, about $7 million was ERCOT ancillary-service money; the rest was resale credits under its TXU contract.[16][17]
  • The commission approved ERCOT's Batch Zero process on June 18, 2026 with 438 gigawatts in the queue, 89% data centers.[36]

From the first controllable load to the audit

2020 → 2026
  1. The operator

    The first controllable load, and a board rebuilt by the storm

    A year before the mines arrive in numbers, ERCOT grants the first load-only Controllable Load Resource designation to a Lancium-operated computing site at Big Spring, the market status through which a mine can sell its flexibility into the reserve services. Then Winter Storm Uri: the board fires Bill Magness in March 2021, and in June the Legislature passes SB 2, cutting the board to eleven with eight members chosen by a committee the governor, lieutenant governor, and speaker appoint, all Texas residents. Brad Jones runs the operator on an interim basis; asked in 2022 whether Texas plans to be the world's mining center, he answers, "Yeah, that's what we are planning." [7][4][3][8]

  2. The load

    The mines fill the queue: 17 gigawatts to 35 in four months

    On March 25, 2022 ERCOT issues an interim interconnection process for loads of 75 megawatts or more, effective immediately, written for a category the notice never names. A Large Flexible Load Task Force meets from April 14. The tracked queue runs from 17,376 megawatts on April 26 to 35,142 on August 22 - against a peak of 80,148 that July - and ERCOT hires a Large Flexible Load Interconnection Manager. The Blockchain Council tells the task force in September that "33,000 MWs is not possible" and that perhaps two gigawatts are actually running. In October seven U.S. senators write Pablo Vegas, a month into the job, naming seven miners drawing more than a gigawatt. [9][10][11][6][12][5][8]

  3. The resource

    The program, and the storm that proved it: 1,530 to 130

    On December 6 ERCOT opens a voluntary curtailment program for "large flexible customers, such as bitcoin mining facilities" - a phone, text, and email request to cut load after non-spinning reserves are deployed and before emergency service is called. Woody Rickerson: "These customers are large power users but have the flexibility and willingness to reduce their energy use quickly, if needed." Winter Storm Elliott arrives before the program goes live, and ERCOT's report records the mines doing it anyway: registered large flexible loads "curtailed their consumption from 1,530 MW to 130 MW (a 91.5% reduction) during the peak demand," all twenty known sites, most once prices passed $70 to $110 a megawatt-hour, with 75 megawatts held as responsive reserve. [13][14]

  4. The resource

    The $31.7 million month, and the $12 billion the monitor did not blame on mines

    Riot reports $31.7 million in credits for curtailing Rockdale by more than 95% at the August peaks, against 333 bitcoin mined, and the press writes that ERCOT paid it; Riot answers that about $24 million were resale credits under its retail contract with TXU and about $7 million ERCOT's ancillary-service payments - "less than one percent of the program, which administered nearly $1 billion." In December the Independent Market Monitor tells the board that ERCOT's new contingency reserve service "generated artificial shortages that produced massive inefficient market costs, totaling more than $12 Billion in 2023" - a critique of how much reserve ERCOT held, in which the mines are not named. Vegas, that fall, on the miners: "I'm interested in their operating characteristics." [16][17][18][19]

  5. The resource

    Heather, the numbers, and the Senate's 40,000 megawatts

    In Winter Storm Heather the mines curtail "on several occasions," ERCOT's operations chief reports, "but the magnitude of response was not consistent day to day." By April the queue holds 40,808 megawatts with 4,479 approved to energize and an observed simultaneous mining peak of 2,538. On June 12 Vegas tells the Senate that peak demand could go from 85 gigawatts to 150 by 2030, more than half of it data centers and miners, and Rickerson puts 40,000 megawatts of mining or flexible load in the queue; the committee's interim report will recommend evaluating miners "acting as 'energy traders.'" In July Rickerson tells the Tribune mining "can draw up to 2,600 megawatts," with as much again approved, and the Lieutenant Governor says it "can't be the Wild Wild West of data centers and crypto miners crashing our grid." [20][21][23][22]

  6. The resource

    Non-firm by definition: how ERCOT plans around the mines

    ERCOT's planning documents write the mines into the grid as a resource. The May 2025 capacity report: "ERCOT assumes all Loads other than Large Flexible Loads (i.e., crypto-currency mining) are considered Firm Loads"; "An LFL is typically a crypto-currency mining site." The long-term forecast carries a "Crypto" category and applies a 49.8% peak factor to the data centers but not to it. The market monitor's 2024 report counts "more than 3,600 MW of non-coincident demand" from mines by year-end, "the vast majority of LFLs." In June ERCOT surveys every data-center and crypto load over 75 megawatts and sets 2,600 megawatts as the most the grid can lose at once without breaching frequency limits. The Legislature passes SB 6 on June 20. [26][25][27][28]

  7. The queue

    "We have outgrown the process": 63 gigawatts to 226

    Kristi Hobbs tells the commission in October that the first wave was "mostly crypto-mining" with "much shorter timeline to interconnect (months rather than years)" and the current wave is AI. In December she tells the board the queue holds about 226 gigawatts against 63 a year earlier, 73% data centers, with 225 new requests in 2025 against 152 in the three years before: "We have outgrown the process that was established for reviewing these large loads. It was originally set up for, we were thinking about 40 to 50 loads back in the 2022 time frame." ERCOT creates an Interconnection and Grid Analysis division and hires McKinsey. The Congressional Research Service reads the same deck as about 20 gigawatts of crypto - nine percent. [29][30][31][42][2]

  8. The resource

    Fern: 4,100 megawatts of mining shed, and 64% of the emergency reserve

    In Winter Storm Fern ERCOT's operations chief reports that "cryptocurrency mining began reducing ~4,100 MW Saturday" - beside 4,200 from oil and gas and 170 from data centers - and that adding the reductions back would have put Monday's peak at 84,558 megawatts; no emergency was declared and no conservation call made. Three weeks earlier ERCOT's own presentation on the emergency reserve service had shown crypto mines at 64% of the capacity procured for the winter, up from nine resources in late 2023 to 75, inside a fixed $75 million budget - and that on September 6, 2023 about 60% of the reserve had switched itself off before ERCOT asked. [33][32]

  9. The queue

    The monitor's verdict, and Batch Zero

    The market monitor's 2025 report: crypto demand about 4,600 megawatts; "all 12 registered CLRs are cryptocurrency mines"; crypto more than 64% of emergency reserve capacity; and "allowing them to provide ERS essentially pays them to do what they would already do" - with a recommendation to move them out of it and a warning that flexible loads "can shift a disproportionate share of transmission costs onto other consumers." ERCOT files NPRR1337 on May 26 to exclude price-responsive loads from the reserve. On June 18 the commission approves Batch Zero - every request studied with every other, twice a year, the first such process at any U.S. grid operator - with 438 gigawatts in the queue, 89% of it data centers. Vegas: "This new process represents a fundamental shift." [34][40][36]

  10. The watch

    A record peak, an audit, and a December filing

    The grid sets its record, 91,089 megawatts, on July 22; Vegas: "The ease at which we got through last week's peaks would not be the way I would characterize the future in two to three years." On August 3 the Governor orders an audit of every data center in the queue before more are approved; ERCOT misses its classification deadline, the commission grants an exception on August 20, and the audit covers 250 to 300 projects with a community-impact review of every crypto facility of 25 megawatts or more. Chad Seely: "Our goal is to head toward a December 10 filing." ERCOT's SB 6 work continues in parallel, including a demand-management service that must exclude any customer "that curtails in response to the wholesale price of electricity" - the mines' whole model. [6][41][37][38][39]

What is ERCOT, and what is it not?

The operator, not the regulator, and not a utility. The Electric Reliability Council of Texas is a membership-based nonprofit that “manages the flow of electric power to 27 million Texas customers – representing about 90 percent of the state's electric load,” running the wholesale market, the interconnection queue, the reserve services, and the programs that ask big customers to stand down; because its wires do not cross a state line, the Federal Energy Regulatory Commission has no jurisdiction over them.[1][2]It answers to a board the Legislature rebuilt after Winter Storm Uri – SB 2 of 2021 cut it to eleven members, eight of them chosen by a committee the governor, lieutenant governor, and speaker appoint, all Texans – and to the Public Utility Commission, which approves its rule changes and writes the rules the statutes require.[3] Whether the mines caused that blackout is a different question, answered on its own page. The board fired Bill Magness in March 2021; Brad Jones ran the operator on an interim basis; Pablo Vegas, from NiSource, was chosen in August 2022 after the governor vetoed at least one candidate, and started October 1.[4][5] The grid he runs set its record, 91,089 megawatts, on July 22, 2026.[6] The regulator that approved everything on this page, and sued to keep the mines' registrations secret, is on the Public Utility Commission and Bitcoin; the sites are on the Texas Bitcoin mining map. This page is the operator's account of the load.

How did the mines arrive in ERCOT's queue?

All at once, and mostly on paper. The market status they would use predates them: in June 2020 ERCOT granted the first load-only Controllable Load Resource designation to a Lancium-run computing site at Big Spring, the registration through which a mine can bid its flexibility into the reserve services like a generator.[7] After China's ban in 2021 the mines came for the cheap West Texas power and the interim chief executive told Bloomberg that a world mining center was “what we are planning.”[8] On March 25, 2022 ERCOT issued an interim interconnection process for loads of 75 megawatts or more, effective immediately and silent on what they were for; a Large Flexible Load Task Force met from April 14; and the tracked queue ran from 17,376 megawatts on April 26 to 35,142 on August 22, against a summer peak of 80,148.[9][10][11][6] The industry itself told the task force in September that “33,000 MWs is not possible” and that perhaps two gigawatts were actually running – the first sign of the duplicate, speculative requests the Legislature would later call phantom load.[12] By January 2023 the queue held 38,143 megawatts “predominantly bitcoin mining”; by April 2024, 40,808, with 4,479 approved to energize and an observed simultaneous mining peak of 2,538.[15][21] In October 2022 seven U.S. senators wrote Vegas, a month into the job, naming seven miners drawing more than a gigawatt and quoting an economist who called them a “tapeworm.”[8] The organizer who briefed the task force is on Lee Bratcher and Bitcoin.

THE LOAD · BITCOIN MINING ON THE ERCOT GRID, MEGAWATTS, BY YEAR8502021TBC estimate1,5302022ERCOT2,3002023ERCOT via Tribune3,6002024IMM4,6002025IMM4,1002026ERCOT2021: industry estimate, 700–1,000 MW · 2022: registered at Elliott's peak, cut to 130 · 2023: ~20 mines, up to 2,300 · 2024: IMM non-coincident peak2025: IMM peak crypto demand · 2026 (amber): not capacity but the ~4,100 MW ERCOT reported mines shedding in Winter Storm FernTBC deck Sept 2022 · ERCOT Elliott report Mar 2023 · Texas Tribune Jan 2024 · Potomac Economics 2024 and 2025 SOM · ERCOT board Feb 2026
The load. Five years of the same industry, counted by the operator and its monitor: a doubling every two years, to something near five gigawatts, of a load that ERCOT's own report treats as the only non-firm class on the grid. The amber bar is the proof of the classification – in the January 2026 storm the mines gave back almost all of it in a weekend.

What did the mines do in the storms?

What ERCOT's program asked, mostly before it asked. On December 6, 2022 ERCOT opened a voluntary curtailment program for “large flexible customers, such as bitcoin mining facilities” – an automated request to cut load after non-spinning reserves are deployed and before emergency service is called – with Woody Rickerson's explanation: “These customers are large power users but have the flexibility and willingness to reduce their energy use quickly, if needed.”[13] Winter Storm Elliott arrived before the program went live, and ERCOT's report recorded the mines doing it on price alone: registered large flexible loads “curtailed their consumption from 1,530 MW to 130 MW (a 91.5% reduction) during the peak demand,” all twenty known sites, most once prices passed $70 to $110 a megawatt-hour, with 75 megawatts held as responsive reserve.[14] In Winter Storm Heather a year later the mines curtailed “on several occasions,” the operations chief reported, “but the magnitude of response was not consistent day to day.”[20] In Winter Storm Fern, in January 2026, the same officer reported that “cryptocurrency mining began reducing ~4,100 MW Saturday” – beside 4,200 from oil and gas and 170 from data centers – and that adding the reductions back would have put Monday's peak at 84,558 megawatts; no emergency was declared and no conservation call was made.[33] In the summers the story is the same and the money is the argument: in August 2023 Riot curtailed Rockdale by more than 95% at the peaks and booked $31.7 million in credits against 333 bitcoin mined, and the press wrote that ERCOT had paid it. Riot's answer: about $24 million were resale credits under its retail contract with TXU, and about $7 million ERCOT's ancillary-service payments, “less than one percent of the program, which administered nearly $1 billion.”[16][17] Vegas, asked about the miners that fall: “I'm interested in their operating characteristics.”[19] The site that curtailed is on Rockdale, Texas and Bitcoin; the company that curtailed it is on Riot Platforms and Texas.

How does ERCOT plan around them?

By definition. The May 2025 Capacity, Demand and Reserves report – the document that says whether Texas has enough power – states: “ERCOT assumes all Loads other than Large Flexible Loads (i.e., crypto-currency mining) are considered Firm Loads … Large Flexible Loads are responsive to real time prices and can reduce consumption or turn off quickly before emergency conditions”; its glossary: “An LFL is typically a crypto-currency mining site.”[26]The long-term load forecast carries a “Crypto” category and applies a 49.8% peak-to-request factor to the data centers but not to it; the operations division has built a crypto demand-forecasting model, though it “does not explicitly model expected price response.”[25][33] The Independent Market Monitor's count: more than 2,000 megawatts of mines identified by spring 2023, “more than 3,600 MW of non-coincident demand and more than 3,200 MW of simultaneous demand” by the end of 2024, about 4,600 megawatts in 2025 – “the vast majority of LFLs in ERCOT are cryptocurrency mines.”[27][34] The Energy Information Administration put the class at 54 billion kilowatt-hours in 2025, a tenth of the grid's consumption.[24] And in June 2025 ERCOT surveyed every data-center and crypto load over 75 megawatts and set 2,600 megawatts as the most the grid can lose in an instant without breaching its frequency limits – the number that became the ride-through rule the commission adopted in July 2026, after twelve large-load trip events in 2025.[28][33] Rickerson, in July 2024: mining “can draw up to 2,600 megawatts” and “represents the largest share of large flexible loads.”[22] The statute that made the planning binding is on Phil King and Bitcoin.

What do the mines sell ERCOT, and what did the monitor say?

Their off switch, and that the price was already buying it. Mines participate three ways: as Controllable Load Resources bidding into the responsive and non-spinning reserves, as price-responsive load that shuts off when the four coincident summer peaks set their transmission bill, and as providers of the Emergency Response Service, a fixed-budget program that pays customers to stand ready to curtail on ERCOT's call. ERCOT's own presentation on January 7, 2026 showed the third: crypto mining “increased to 64% of the total capacity procured” for the winter term, from nine resources in late 2023 to seventy-five, inside a $75 million annual budget – and on September 6, 2023, about 60% of the reserve had switched itself off before ERCOT instructed it.[32] The market monitor's 2025 report, published in June 2026, drew the conclusion: “all 12 registered CLRs are cryptocurrency mines”; crypto exceeds 64% of emergency reserve capacity; and because those mines “are responsive to real time prices,” “allowing them to provide ERS essentially pays them to do what they would already do” – with a recommendation to move them out of the service, and a warning that flexible loads “can shift a disproportionate share of transmission costs onto other consumers.”[34] ERCOT filed NPRR1337 on May 26, 2026 to add a baseline test excluding price-responsive loads from the service, and the demand-management service SB 6 requires must, by ERCOT's own reading, exclude any customer “that curtails in response to the wholesale price of electricity.”[40][39] Two corrections the record requires. The monitor's complaint that ERCOT's contingency reserve service “generated artificial shortages that produced massive inefficient market costs, totaling more than $12 Billion in 2023” was about how much reserve ERCOT chose to hold; the mines are not named in it.[18] And the Senate committee that heard Vegas in June 2024 recommended, in its interim report, evaluating miners “acting as ‘energy traders’” – the frame the Legislature has since adopted.[23] The senator who wrote the registry the commission enforces is on Nathan Johnson and Bitcoin.

THE RESERVE · THE MINES INSIDE ERCOT'S SERVICES, AND WHAT THE MONITOR SAID12 of 12registered controllable loadsall crypto mines · 2025 SOM64%of emergency reserve capacityDec 2025–Mar 2026 · ERCOT deck9 → 75crypto resources in ERSlate 2023 → winter 2025–26$75Mfixed annual ERS budgetERCOT · Jan 7, 2026~60%self-deployed before instructionSept 6, 2023 · ERCOT deck~$7MERCOT's share of Riot's $31.7MAug 2023 · the rest was TXU$12Bthe ECRS critiqueIMM Dec 2023 · mines not namedNPRR1337to exclude price-responsive loadsfiled May 26, 2026“allowing them to provide ERS essentially pays them to do what they would already do” – Independent Market Monitor, 2025 State of the MarketPotomac Economics 2025 SOM · ERCOT ERS crypto-mining presentation Jan 7, 2026 · Riot Sept 8, 2023 · IMM board report Dec 11, 2023 · OBM on NPRR1337
The reserve. Green is the mines' position inside ERCOT's services; amber is the evidence that the position pays for behavior the price already buys. The two grey tiles are the corrections the record requires – the operator's money in Riot's famous month was a fifth of the headline, and the monitor's twelve-billion-dollar complaint was about how much reserve ERCOT bought, not who sold it.

What happened to the queue?

It stopped being about mines. Kristi Hobbs told the commission in October 2025 that the first wave was “mostly crypto-mining” with a “much shorter timeline to interconnect (months rather than years)” and that the current wave was AI data centers; in December she told the board the queue held about 226 gigawatts against 63 a year earlier, 73% data centers, with 225 new requests in 2025 against 152 in the three years before: “We have outgrown the process that was established for reviewing these large loads. It was originally set up for, we were thinking about 40 to 50 loads back in the 2022 time frame.”[29][30][31] The Congressional Research Service read the same deck as about 20 gigawatts of crypto – nine percent.[2] ERCOT created an Interconnection and Grid Analysis division and hired McKinsey.[42] By April 2026 the queue was 410 gigawatts, 87% data centers; on June 18 the commission approved Batch Zero – NPRR1325 and PGRR145, every request studied with every other twice a year, loads energized before July 10 counted as base – with 438 gigawatts pending, “the first time any U.S. ISO has implemented a batch assessment process.” Vegas: “This new process represents a fundamental shift in how ERCOT manages the significant growth of large load interconnection.”[35][36] On July 22 the grid set its record; Vegas, a week later: “The ease at which we got through last week's peaks would not be the way I would characterize the future in two to three years. I think it will be much more difficult.”[6][41] On August 3 the Governor cited 474 gigawatts and ordered an audit of every data center before more are approved; ERCOT missed its August 7 classification deadline, the commission granted an exception on August 20, and the audit covers 250 to 300 projects with a community-impact review of every crypto facility of 25 megawatts or more. Chad Seely: “Our goal is to head toward a December 10 filing.”[37][38] The chairman who will hear the results is on Ken King and Bitcoin.

The honest counterweight: the monitor, the money, and the process

Three things, and the operator's own documents supply all of them. First, the monitor. ERCOT built the market status the mines use, wrote them into its plans as the grid's only non-firm load, and let them fill two-thirds of an emergency service – and the analyst it pays to watch its market concluded that the service pays them for what the price already buys, and that their flexibility shifts transmission costs onto everyone else.[7][26][34]ERCOT's response, NPRR1337, came the month before the report. Second, the money, which cuts the other way. The headline figures – Riot's $31.7 million month, the monitor's twelve billion – are not ERCOT paying miners: a fifth of the first was ERCOT's and none of the second was about them, and ERCOT has never published what its services pay the mines in total.[17][18] What it has published is what the mines did when it mattered: 91.5% in Elliott, four gigawatts in Fern, on price, before any instruction.[14][33] Third, the process. The interim interconnection rule of March 2022 was still the rule in 2026; the curtailment program was “temporary” and never replaced; the task force went inactive; and the operator's own planning chief said it had outgrown a process built for fifty loads while it held requests for four hundred gigawatts.[9][13][10][31] The mines were the first to show ERCOT that its queue could be gamed and the first to show it that load could be a resource. Both lessons arrived in 2022. The rules for the first came in 2026.

The fair reading is that ERCOT has been the mines' most useful institution and their most honest one: it built the product they sell, counted them accurately when no one else would, credited them in every storm report, and then published the analysis that says it has been overpaying them. The question its own monitor has put to it – whether a load that switches off for the price should also be paid to promise to – is the question the Legislature's demand-management service answers no, and ERCOT's rule change would answer no, and the mines' business model needs answered yes.

Where does ERCOT stand today?

As of September 2026: a record peak three months old, a queue of 474 gigawatts under audit with a December 10 filing targeted, Batch Zero paused at classification, NPRR1337 pending, a demand-management service being designed to exclude the mines, and a chief executive telling Texans the next two or three summers will be harder.[6][38][40][39][41] The mines that sit inside it – about 4,600 megawatts, less than a tenth of what is waiting behind them – are on the Texas Bitcoin mining map; the regulator that oversees the operator is on the Public Utility Commission and Bitcoin; the statute-by-statute record ERCOT implements is on the Texas Bitcoin law timeline. This page is the load the operator counts as a resource, and the price it has decided that resource is worth.

Frequently asked questions

What is ERCOT, and how is it different from the Public Utility Commission?

ERCOT, the Electric Reliability Council of Texas, is the nonprofit grid operator for about 90 percent of the state's load - 27 million customers - running the wholesale market, the interconnection queue, the reserve services, and the curtailment programs, outside federal jurisdiction because its grid does not cross state lines. Its board was rebuilt by SB 2 in 2021 after Winter Storm Uri, with eight of eleven members chosen by a committee the governor, lieutenant governor, and speaker appoint. Pablo Vegas has been its chief executive since October 1, 2022. The Public Utility Commission is the five-member state agency that oversees ERCOT, approves its rule changes, and writes the rules the Legislature's statutes require; it has its own page.

How does ERCOT treat Bitcoin mines?

As a load it can switch off. ERCOT's capacity report states that 'all Loads other than Large Flexible Loads (i.e., crypto-currency mining) are considered Firm Loads' and that 'an LFL is typically a crypto-currency mining site'; its long-term forecast carries a 'Crypto' category. Mines can register as Controllable Load Resources - all twelve registered in 2025 were crypto mines - and sell their flexibility into the responsive and emergency reserve services. In Winter Storm Elliott the registered mines cut from 1,530 to 130 megawatts at the peak; in Winter Storm Fern in January 2026 ERCOT reported 'cryptocurrency mining began reducing ~4,100 MW.'

How much does ERCOT pay Bitcoin miners?

Less than the headlines say, and ERCOT publishes no total. When Riot reported $31.7 million in credits for August 2023, about $24 million were resale credits under its retail power contract with TXU and about $7 million were ERCOT ancillary-service payments - 'less than one percent of the program, which administered nearly $1 billion,' Riot said. The Independent Market Monitor's 2025 report found crypto mines held more than 64% of the emergency reserve service's capacity, inside a fixed $75 million annual budget, and concluded that 'allowing them to provide ERS essentially pays them to do what they would already do.' ERCOT filed NPRR1337 in May 2026 to exclude price-responsive loads from that service.

How much Bitcoin mining is on the ERCOT grid?

By ERCOT's and its monitor's figures: about 1,530 megawatts registered at the December 2022 peak, up to 2,300 across some twenty industrial mines by late 2023, more than 3,600 megawatts of non-coincident demand by the end of 2024, and about 4,600 megawatts in 2025. The Energy Information Administration put large flexible loads at 54 billion kilowatt-hours in 2025, roughly a tenth of ERCOT's consumption. By late 2025 crypto was about nine percent of a 226-gigawatt queue that was 73% data centers; by August 2026 the queue was 474 gigawatts, 90% data centers.

What is Batch Zero?

ERCOT's replacement for studying large loads one at a time. Kristi Hobbs told the board in December 2025 that 'we have outgrown the process,' which had been designed for forty or fifty loads in 2022. Under NPRR1325 and PGRR145, approved by the commission on June 18, 2026, all pending requests are studied together every six months; loads energized before July 10, 2026 are base load, the rest studied. It was the first batch process at any U.S. grid operator. On August 3 the Governor ordered an audit of every data center in the queue before more are approved; the commission granted ERCOT an extension on August 20, and the audit includes a community-impact review of every crypto facility of 25 megawatts or more, with a filing targeted for December 10.

Sources

Primary record first: ERCOT's own reports, board decks, market notices, releases, and legislative presentations, read directly; the Independent Market Monitor's State of the Market reports; the Senate committee's interim report; Riot's SEC filing and response; the Energy Information Administration and the Congressional Research Service; then the Texas Tribune and Utility Dive for the quotes and the audit. This is a research and reference article, not financial, investment, or legal advice.

  1. [1]ERCOT - Company profile: 27 million customers, about 90 percent of the state's electric load; a membership-based 501(c)(4) nonprofit under a board of directors, the Public Utility Commission, and the Legislature
  2. [2]Congressional Research Service - R48914 (April 22, 2026), quoting FERC: transmission wholly within ERCOT "is not subject to the Commission's jurisdiction" under the Federal Power Act; about 20 GW of the 2025 queue for cryptocurrency mining
  3. [3]Texas Legislature Online - SB 2 (87R) enrolled text: the ERCOT board rebuilt - eleven members, eight chosen by a selection committee appointed by the governor, lieutenant governor, and speaker; Texas residency
  4. [4]Texas Tribune - ERCOT board fires CEO Bill Magness (March 3–4, 2021)
  5. [5]Texas Tribune - ERCOT picks Pablo Vegas as new CEO (August 16, 2022): from NiSource; started October 1, 2022; the governor had vetoed at least one candidate
  6. [6]ERCOT - Peak demand records: 91,089 MW on July 22, 2026 (unofficial); 85,508 MW on August 10, 2023; 80,148 MW on July 20, 2022
  7. [7]PR Newswire - Lancium and MP2 Energy offer demand-response solution for high-throughput computing and cryptocurrency miners (June 19, 2020): "the first successful load-only Controllable Load Resource (CLR) designation by ERCOT"
  8. [8]Senators Warren, Markey, et al. - letter to ERCOT CEO Pablo Vegas (October 12, 2022, PDF): seven miners drawing more than 1,045 MW with 2,399 MW planned; interim CEO Brad Jones on Texas as the world's mining center - "Yeah, that's what we are planning"; Ed Hirs's "tapeworm"
  9. [9]ERCOT - Market notice W-A032522-01 (March 25, 2022): the interim large-load interconnection process, effective immediately - standalone loads of 75 MW or more, co-located 20 MW or more
  10. [10]ERCOT - Large Flexible Load Task Force (inactive): first meeting April 14, 2022; chair Bill Blevins; succeeded by the Large Load Working Group
  11. [11]ERCOT - Large Load Interconnection queue status update (August 22, 2022, PDF): 17,376 MW tracked on April 26, 2022, 35,142 MW on August 22; a Large Flexible Load Interconnection Manager hired
  12. [12]Texas Blockchain Council - deck to the Large Flexible Load Task Force (September 26, 2022, ERCOT-hosted PDF): "33,000 MWs is not possible"; 1,500 to 2,000 MW energized in Texas in 2022
  13. [13]ERCOT - ERCOT creates voluntary curtailment program for large flexible loads (December 6, 2022): Rickerson - "These customers are large power users but have the flexibility and willingness to reduce their energy use quickly, if needed"
  14. [14]ERCOT - December 2022 cold-weather operations public report (March 27, 2023, PDF), § 12: large flexible loads "curtailed their consumption from 1,530 MW to 130 MW (a 91.5% reduction) during the peak demand"; 75 MW of responsive reserve; all twenty known sites curtailed, most above $70 to $110 per MWh
  15. [15]Baker Botts - Bitcoin and large loads in ERCOT (April 2023): 38,143 MW of large flexible loads in the queue in January 2023, "predominantly bitcoin mining," against an 80,038 MW peak
  16. [16]Riot Platforms - Form 8-K exhibit (September 6, 2023): $31.7 million in power and demand-response credits for August 2023 against 333 bitcoin mined; curtailed "by more than 95% during periods of peak demand"
  17. [17]Riot Platforms - Riot responds to recent inquiries regarding its power strategy (September 8, 2023): about $24 million were resale credits under its TXU contract and about $7 million ERCOT ancillary-service credits, "less than one percent of the program, which administered nearly $1 billion"
  18. [18]ERCOT - Independent Market Monitor report to the board (December 11, 2023, PDF): ECRS "generated artificial shortages that produced massive inefficient market costs, totaling more than $12 Billion in 2023"
  19. [19]Texas Tribune - Texas Bitcoin miners profit from a strained grid (January 3, 2024): about twenty industrial mines up to 2,300 MW; Vegas - "I'm interested in their operating characteristics"; Hirs - "Why can't I get $5 a kilowatt an hour for shutting down my power?"
  20. [20]ERCOT - System operations update to the board (February 19, 2024, PDF): Winter Storm Heather peak 78,495 MW; large flexible loads curtailed "on several occasions" but "the magnitude of response was not consistent day to day"
  21. [21]ERCOT - Large Load Interconnection status update (April 1, 2024, PDF): about 40,808 MW in the queue; 4,479 MW approved to energize; observed simultaneous peak 2,538 MW
  22. [22]Texas Tribune - Texas Bitcoin mine noise, power grid, and the Legislature (July 10, 2024): Rickerson - mining "can draw up to 2,600 megawatts," another 2,600 approved; "the largest share of large flexible loads"; Patrick - "It can't be the Wild Wild West of data centers and crypto miners crashing our grid"
  23. [23]Texas Senate Business and Commerce Committee - interim report to the 89th Legislature (December 2024, PDF): ERCOT's June 12, 2024 estimate of 40,000 MW of mining or large flexible load in the queue; recommends evaluating miners acting as "energy traders"
  24. [24]U.S. Energy Information Administration - Today in Energy (October 3, 2024): large flexible loads about 54 billion kWh in 2025, roughly 10% of ERCOT consumption; 5,479 MW approved; 65% historical utilization
  25. [25]ERCOT - 2025 Long-Term Load Forecast report (April 8, 2025, PDF): a "Crypto" category; a 49.8% peak-to-request factor applied to non-crypto data-center additions
  26. [26]ERCOT - Capacity, Demand and Reserves report (May 2025, revised, PDF): "ERCOT assumes all Loads other than Large Flexible Loads (i.e., crypto-currency mining) are considered Firm Loads"; "An LFL is typically a crypto-currency mining site"
  27. [27]Potomac Economics - 2024 State of the Market report for ERCOT (June 2025, PDF): "The vast majority of LFLs in ERCOT are cryptocurrency mines"; more than 3,600 MW non-coincident and 3,200 MW simultaneous by the end of 2024
  28. [28]ERCOT - Market notice M-B062325-01 (June 23, 2025): survey of data-center and crypto loads of 75 MW or more; about 2,600 MW the maximum sustainable sudden load loss
  29. [29]ERCOT via PUC Interchange - Kristi Hobbs presentation, Project 55999 (October 23, 2025, PDF): the initial wave "Mostly crypto-mining" with "much shorter timeline to interconnect (months rather than years)"; the current wave AI data centers; flexible loads "could utilize available transmission capacity if they are willing to curtail"
  30. [30]ERCOT - System planning and weatherization update to the board (December 2025, PDF): about 226 GW seeking interconnection against 63 GW in December 2024, about 73% data centers; 225 new requests in 2025 against 152 in 2022–2024
  31. [31]Utility Dive - ERCOT's large-load queue jumped almost 300% last year (January 6, 2026): Hobbs - "We have outgrown the process that was established for reviewing these large loads. It was originally set up for, we were thinking about 40 to 50 loads back in the 2022 time frame"
  32. [32]ERCOT - ERS crypto-mining load presentation (January 7, 2026, PPTX): crypto mining "increased to 64% of the total capacity procured" for the December 2025 to March 2026 term; from 9 crypto ERS resources in late 2023 to 75; a fixed $75 million annual budget; on September 6, 2023 about 60% of ERS self-deployed before instruction
  33. [33]ERCOT - System operations update to the board (February 2026, revised, PDF): Winter Storm Fern - "Cryptocurrency mining began reducing ~4,100 MW Saturday"; oil and gas about 4,200 MW, data centers 170 MW; adding reductions back "brings Monday morning peak to 84,558 MW"; twelve large-load ride-through events in 2025; a crypto demand-forecasting model implemented
  34. [34]Potomac Economics - 2025 State of the Market report for ERCOT (June 2026, PDF): crypto demand about 4,600 MW in 2025; "all 12 registered CLRs are cryptocurrency mines"; crypto more than 64% of ERS capacity; "allowing them to provide ERS essentially pays them to do what they would already do"; flexible loads "can shift a disproportionate share of transmission costs onto other consumers"
  35. [35]ERCOT - Large-load update to Senate Business and Commerce (April 1, 2026, PDF): about 410 GW tracked, about 87% data centers
  36. [36]ERCOT - PUCT approves ERCOT's new large-load interconnection process (June 18, 2026): NPRR1325 and PGRR145, Batch Zero; 438 GW in the queue, about 89% data centers; Vegas - "This new process represents a fundamental shift"; the first batch process at any U.S. grid operator
  37. [37]ERCOT - Market notices M-A080326-01 and M-A080326-02 (August 3 and 20, 2026): the Governor's audit directive; the classification deadline missed; the commission's good-cause exception granted
  38. [38]Utility Dive - ERCOT, Texas PUC launch data center audit (August 21, 2026): a community-impact review of crypto facilities of 25 MW and above; 157 medium data-center and crypto facilities; Seely - "Our goal is to head toward a December 10 filing"; the April 9, 2027 study date will slip
  39. [39]ERCOT - 89th Legislative Session status deck (July 2026, PDF): the SB 6 assignments - curtailment thresholds, a demand-management service that must exclude any customer "that curtails in response to the wholesale price of electricity," breaker protocols, the net-metering study
  40. [40]OBM - NPRR1337: what ERCOT's proposed ERS changes mean for Bitcoin miners (2026): an alternate-baseline test, filed May 26, 2026, to exclude price-responsive loads from the emergency reserve service
  41. [41]Texas Tribune - Texas power grid sets a record; Vegas on what comes next (July 29, 2026): "The ease at which we got through last week's peaks would not be the way I would characterize the future in two to three years. I think it will be much more difficult"
  42. [42]ERCOT - ERCOT announces strategic organizational changes (December 12, 2025): a new Interconnection and Grid Analysis division under Jeff Billo; McKinsey engaged on a queue of "over 225 gigawatts"