Riot Platforms: The Miner That Became a Landlord

The largest Bitcoin miner in Texas is a Colorado company that was a veterinary-diagnostics shell until October 2017, when it changed its name and its share price rose by half in a week. It bought its way into the state four years later, taking the old Alcoa site at Rockdale for six hundred and fifty million dollars in stock and cash, and it learned there what no other miner has proved so publicly: that in a Texas August the most profitable thing a seven-hundred-megawatt mine can do is stop. It fought the Legislature's brake, sued the federal government over a survey, was refused by one county and approved by another, and in 2026 rented a hundred and ninety-one megawatts of Rockdale to an AI lab for twenty years and nine billion dollars, selling seven thousand bitcoin in six months to pour the concrete. The company's filings tell three stories about the same site – the miner's, the landlord's, and the shareholder's – and this page is all three.

By TexasBitcoin · Published September 26, 2026 · Updated September 26, 2026

The short answer

Riot Platforms is the Nasdaq-listed Bitcoin miner, headquartered in Castle Rock, Colorado, that owns the largest mine in North America at Rockdale, Texas – 700 developed megawatts, acquired with Whinstone in May 2021 – and a 400-megawatt first phase of a planned gigawatt at Corsicana. It earned $71.2 million in power credits for curtailing in 2023 and $56.7 million in 2025, testified against the 2023 mining brake and for the 2025 Bitcoin reserve, and since January 2025 has been converting its Texas sites to data centers: AMD leases 50 megawatts at Rockdale, and on August 10, 2026 Riot announced a twenty-year, 191-megawatt, $9.1 billion lease with an unnamed frontier AI lab.

Key facts

  • Riot agreed to buy Whinstone on April 8, 2021 for $80 million cash and 11.8 million shares, about $651 million at announcement, closing May 26, 2021.[6][7]
  • In August 2023 Riot booked $31.7 million in credits against 333 bitcoin mined - $24.2 million from power sold under its TXU contract and $7.4 million from ERCOT demand response.[14]
  • Riot's power credits were $71.2 million in 2023, $33.7 million in 2024, and $56.7 million in 2025.[17][29][33]
  • Navarro County refused Riot's reinvestment zone on March 11, 2024 and approved a ten-year abatement 3–2 on October 15, 2024.[20][26]
  • On August 10, 2026 Riot announced a twenty-year, 191-megawatt lease at Rockdale with a frontier AI lab, about $9.1 billion in base rent.[39]
  • Riot reported a net loss of $663.2 million for 2025 and held 11,380 bitcoin on June 30, 2026, down from 18,005 at year-end.[33][39]

From the shell to the lease

2017 → 2026
  1. The shell

    Bioptix becomes Riot Blockchain, and the SEC comes calling

    A Castle Rock, Colorado veterinary-diagnostics shell renames itself Riot Blockchain on October 4, 2017; the stock rises by half in a week and several-fold in three months, and CNBC's investigation that February finds a company with more promise than product. The SEC issues a subpoena on April 9, 2018; the chief executive, John O'Rourke, resigns that September after being named in an unrelated $27 million manipulation case; a shareholder suit follows. The investigation closes on January 29, 2020 with no enforcement recommended, and the suit is eventually dismissed with prejudice. [1][2][3][4][18]

  2. The miner

    Jason Les, and the largest mine in North America

    Jason Les, a director since 2017 and a former professional poker player, becomes chief executive on February 8, 2021 - "Bitcoin positioned to disrupt the global financial system." On April 8 Riot agrees to buy Whinstone US, the operator of the old Alcoa site at Rockdale, for $80 million in cash and 11.8 million shares, about $651 million at that day's price; the deal closes May 26. "The most significant milestone in Riot's history," Les says. Rockdale, expanded to 700 developed megawatts by 2023, becomes what the company's filings call "the largest single Bitcoin mining facility in North America." [5][6][7][18]

  3. The counties

    Corsicana: a gigawatt announced, and the neighbors organize

    On April 27, 2022 Riot announces a one-gigawatt, immersion-cooled campus on 265 acres in Navarro County, first phase 400 megawatts. Within seven weeks the Concerned Citizens of Navarro County are protesting - "We do not want this" - over water, noise, and the tax breaks to come. The year ends with revenue of $259 million and a net loss of $509.6 million. [8][9][10]

  4. The grid

    Riot Platforms, the Senate, and the $31.7 million month

    Renamed Riot Platforms on January 3, 2023, the company sends its research chief Pierre Rochard to testify against Kolkhorst's SB 1751 on March 28 - "Bitcoin miners are the number 1 employer in Rockdale. Bitcoin miners are also the number 1 taxpayer to Rockdale ISD." In August it curtails Rockdale by more than 95% at the peaks and books $31.7 million in credits against 333 bitcoin mined - "a landmark month," Les says - and the press reports that Texas paid it more not to mine than to mine. Riot's answer two days later: $24.2 million were resale credits under its fixed-price contract with TXU and $7.4 million ERCOT's, "less than one percent of the program." The year's credits total $71.2 million against $189 million of mining revenue. [11][12][13][14][15][16][17]

  5. The counties

    The survey suit, the county that said no, and the one that said yes

    On February 23, 2024 Riot and the Texas Blockchain Council sue the Department of Energy over an emergency survey of miners' power use and win a restraining order in a day; the survey is withdrawn by March 1. On March 11 Navarro County's commissioners unanimously refuse Riot's reinvestment zone - "They created a lot of controversy" - and on April 18 the 400-megawatt Corsicana substation is energized anyway. In May Riot launches a hostile bid for Bitfarms and builds a stake near a fifth of the company before settling in September for a board seat. On October 15 Navarro County passes the abatement 3–2: ten years, $640 million pledged, 140 jobs. The halving cuts the year's credits to $33.7 million and its bitcoin to 4,828, but a new accounting rule turns the year into $109.4 million of net income. [19][20][21][23][25][26][29]

  6. The landlord

    The pivot: 600 megawatts of Corsicana turned toward AI

    On January 21, 2025 Riot announces a formal evaluation of about 600 megawatts at Corsicana for AI and high-performance computing, halts the second mining phase, cuts its hashrate target from 46.7 to 38.4 exahash, and trims $245 million of capital spending. On February 13 it seats three new directors "with constructive, independent input from each of Starboard Value LP and The D. E. Shaw Group" - the activists who had pushed for the turn. That week Rochard tells the Senate the state should buy bitcoin: "now is the perfect time to make a strategic investment." [27][28][44]

  7. The miner

    Rhodium, the loss-making contract, and the $83.5 million pay year

    On April 28 Riot closes the $185 million purchase of Rhodium's 125 megawatts at Rockdale, ending a hosting contract inherited with Whinstone that "generated a gross loss of approximately $15 million" the year before. In June the proxy discloses that Les's 2024 compensation was $83,532,328, most of it a $75.2 million performance-share grant, against a median employee's $58,875 - a ratio of 1,419 to one. The year ends with revenue of $647.4 million, a net loss of $663.2 million, and power credits of $56.7 million, "nearly $10,000 per Bitcoin mined." [30][31][33]

  8. The landlord

    AMD, the deed to Rockdale, and a 75% abatement

    On January 16, 2026 Riot signs its first data-center tenant, AMD, for 25 megawatts at Rockdale over ten years, about $311 million, with options to 200 - and buys the 200-acre site outright for $96 million, funded by selling about 1,080 bitcoin. In February Milam County's commissioners vote 4–1 for a 75% abatement over ten years from 2028; the dissenter: "I thought that was too steep." Riot pays $20 million to settle the last inherited Whinstone claim. By March the proxy shows about 378 million shares, four and a half times the 84 million of 2021, and Les's 2025 pay at $3.46 million with no long-term grant "in direct response to 2025 Say-on-Pay feedback." [34][35][36][38]

  9. The landlord

    The $9.1 billion lease: 191 megawatts to a frontier AI lab

    The second 25 AMD megawatts are exercised in April; Riot signs a non-binding letter of intent for all 756 megawatts of Corsicana's planned capacity with a single tenant; and on August 10, 2026 it announces a twenty-year, 191-megawatt lease at Rockdale with "one of the world's leading frontier AI labs" - about $9.1 billion in base rent to June 2048, 96 megawatts by December 2027, the rest by June 2028. Bloomberg names Anthropic; "Riot declined to comment and Anthropic didn't respond." Les: "a defining moment in our evolution into a leading developer of large-scale data centers." The same filing reports a $237.2 million quarterly loss and 11,380 bitcoin held, down from 18,005 at year-end after some 7,000 were sold to build. Eight days later the Governor announces Riot has committed to comply with his data-center standards, and Les publishes an open letter of support. [37][39][40][41][42]

Where did Riot come from?

A rename. Bioptix, Inc., a Castle Rock, Colorado maker of veterinary diagnostics, became Riot Blockchain, Inc. on October 4, 2017, and its shares rose by half within the week and several-fold within three months; CNBC's investigation the following February found a company whose principal asset was the word in its name.[1][2] The SEC issued a subpoena on April 9, 2018; that September the chief executive, John O'Rourke, resigned after being named in an unrelated $27 million market-manipulation case; a shareholder suit followed.[3][4] The investigation closed on January 29, 2020 with no enforcement recommended, and the suit was dismissed with prejudice in August 2023.[3][18] The company's principal office is still in Castle Rock; its executive chairman since May 2021 is Benjamin Yi, and its chief executive since February 8, 2021 is Jason Les, a director since 2017 and a former professional poker player – “Bitcoin positioned to disrupt the global financial system,” he said on appointment.[32][5] Ten weeks later he bought Texas.

What did Riot buy, and where?

Rockdale first, then Corsicana, then whatever was next to them. On April 8, 2021 Riot agreed to acquire Whinstone US, the operator of the old Alcoa smelter site in Milam County, for $80 million in cash and 11.8 million shares – about $651 million at that day's price – and closed on May 26: “the most significant milestone in Riot's history.”[6][7] Expanded to 700 developed megawatts by 2023, Rockdale is, in the company's filings, “believed to be the largest single Bitcoin mining facility in North America”; the ground it stands on Riot bought outright in January 2026 for $96 million, funded by selling about 1,080 bitcoin.[18][34] On April 27, 2022 it announced a second campus in Navarro County: a gigawatt on 265 acres outside Corsicana, immersion-cooled, 400 megawatts in the first phase; the substation was energized April 18, 2024.[8][21] Around them it bought what it had inherited: $185 million for Rhodium's 125 megawatts at Rockdale in April 2025, ending a hosting contract that “generated a gross loss of approximately $15 million” in 2024, and $20 million to settle a Japanese client's claim from the Whinstone era.[30][36] It also bought Block Mining's Kentucky sites for $92.5 million in July 2024, and in 2024 tried and failed to buy Bitfarms, building a stake near a fifth of the company before settling for a board seat.[24][23][25] The site's own history, from Alcoa to Bitmain to Whinstone, is on Rockdale, Texas and Bitcoin; where it sits among the state's mines is on the Texas Bitcoin mining map.

How does Riot make money from the grid?

By buying power at a fixed price and selling it back when the price is not. Riot's 10-K describes three blocks of power under long-term contract with TXU Energy at Rockdale – 130, 65, and 150 megawatts, fixed-price, running to 2027 and 2030 – with the right to “elect to sell that power in exchange for credits against future power costs,” beside participation in ERCOT's ancillary services and the four-coincident-peak program that sets its transmission bill.[32] The company reports the results as “power credits”: $6.5 million in 2021, $27.3 million in 2022, $71.2 million in 2023 – about 38% of that year's mining revenue, or the equivalent of 2,497 bitcoin – $33.7 million in 2024 after the halving, and $56.7 million in 2025, “nearly $10,000 per Bitcoin mined.”[10][17][29][33]August 2023 is the month everyone cites. Riot curtailed Rockdale by more than 95% at the peaks and booked $31.7 million against 333 bitcoin mined – “a landmark month,” Les said – and CNBC reported that Texas had paid it more to stop than it earned by mining.[14] The filing itself gives the split the headline lost: $24.2 million was power sold under the TXU agreement, $7.4 million ERCOT demand response; Riot's response two days later called its ERCOT share “less than one percent of the program, which administered nearly $1 billion”; the Dallas Morning News put ERCOT's payments to Riot that summer at about $13 million.[14][15][16] The grid operator's side of the arrangement – what it buys from the mines, and what its monitor thinks of the price – is on ERCOT and Bitcoin.

THE SWITCH · POWER CREDITS, $ MILLIONS, BESIDE BITCOIN MINED, BY YEAR$6.5M20213,812 BTCWhinstone closes May 26$27.3M20225,554 BTCnet loss $509.6M$71.2M20236,626 BTCthe $31.7M August$33.7M20244,828 BTCthe halving$56.7M20255,686 BTC“nearly $10,000 per Bitcoin”Credits = resale of fixed-price TXU power plus ERCOT ancillary and demand-response payments, as Riot reports them · 2023: ~38% of mining revenue · 2025: ~10%Riot full-year results 2022–2025 · Form 8-K Sept 6, 2023 · Riot response Sept 8, 2023 · Dallas Morning News Oct 5, 2023
The switch. Five years of the two things a Texas mine sells – hashes and the promise to stop – in the company's own accounting. The 2023 bar is the year the second product briefly rivaled the first, and the year the state noticed. Most of every bar is not ERCOT's money but Riot's own cheap contract power, sold back into a hot market.

What is Riot's record with the counties and the Capitol?

One refusal, two abatements, one lawsuit won, two bills argued. Navarro County's commissioners voted unanimously on March 11, 2024 to deny Riot's reinvestment zone – it had sought 50% for ten years – with Commissioner David Brewer saying, “I don't think it's a good investment. They created a lot of controversy”; the Concerned Citizens of Navarro County had been protesting since June 2022 over water and noise, and Riot's David Schatz had told the town that “the only thing that we do as far as water consumption is just topping off our retention pond.”[20][9][22] On October 15, 2024 the same court passed the abatement 3–2: ten years on new value, against a pledge of $640 million and 140 jobs.[26] Milam County followed in February 2026 with 75% for ten years from 2028, 4–1, the dissenter calling it “too steep.”[35] At the Capitol, Riot's research chief Pierre Rochard testified against Kolkhorst's SB 1751 on March 28, 2023 – “Bitcoin miners are the number 1 employer in Rockdale. Bitcoin miners are also the number 1 taxpayer to Rockdale ISD” – and for the Strategic Bitcoin Reserve in February 2025: “now is the perfect time to make a strategic investment.”[12][13][44] In February 2024 Riot and the Texas Blockchain Council sued the Department of Energy over an emergency survey of miners' power use and had it withdrawn within a week.[19] Its federal lobbying rose from $280,000 in 2022 to $1.16 million in 2024, led by Brian Morgenstern, a former White House deputy press secretary who sits on the council's board.[43] In August 2026, when the Governor ordered an audit of every data center in the queue, Riot was the first company he announced had committed to comply, and Les published an open letter: “We support your commonsense principles of ratepayer protection, water stewardship.”[41][42] The senator whose brake it fought is on Lois Kolkhorst and Bitcoin; the council it sued beside is on Lee Bratcher and Bitcoin; the reserve it argued for is on the Texas Strategic Bitcoin Reserve reference.

What is the pivot?

The conversion of a miner's power into a landlord's. On January 21, 2025 Riot announced a formal evaluation of about 600 megawatts at Corsicana for AI and high-performance computing, halted the second mining phase there, cut its hashrate target from 46.7 to 38.4 exahash, and trimmed $245 million of capital spending – “maximizing the potential of our assets,” Les said.[27] On February 13 it seated three new directors “with constructive, independent input from each of Starboard Value LP and The D. E. Shaw Group,” the activist investors who had pushed for the turn.[28]The tenants came a year later. On January 16, 2026 AMD signed for 25 megawatts at Rockdale over ten years with options, about $311 million; the second 25 followed in April, about $636 million in all.[34][37] In April Riot signed a non-binding letter of intent for all 756 megawatts of Corsicana's planned data-center capacity with a single undisclosed tenant.[37] And on August 10, 2026 it announced a twenty-year lease of 191 megawatts at Rockdale to “one of the world's leading frontier AI labs” – about $9.1 billion in base rent to June 2048, $16.1 billion with extensions, 96 megawatts by December 2027 and the rest by June 2028, financed in part by a $573 million bridge from Morgan Stanley. “A defining moment in our evolution into a leading developer of large-scale data centers,” Les said.[39] Bloomberg identified the tenant as Anthropic; “Riot declined to comment and Anthropic didn't respond.”[40] The company is still a miner – 44.4 exahash in mid-2026, about 4.6% of the network, 5,686 bitcoin mined in 2025 – but the hashrate grows in Kentucky now, and the Texas megawatts are being leased.[39][32] The industry-wide version of the same turn is on the Texas Bitcoin mining map.

THE LEDGERS · THE MINER, THE LANDLORD, THE SHAREHOLDER · SEPTEMBER 2026THE MINERRockdale 700 MW · Corsicana 400 of 1,000Hashrate 12.4 → 44.4 EH/s (2023 → mid-2026)Bitcoin mined 5,686 (2025)All-in power 3.0¢/kWh (Q1 2026)THE LANDLORDAMD · 50 MW · ~$636M · 10 yrsFrontier AI lab · 191 MW · ~$9.1B · 20 yrsCorsicana · 756 MW · non-binding LOIRockdale land bought · $96M · Jan 2026THE SHAREHOLDERShares 84M (2021) → ~378M (2026)Net loss $663M (2025) · $237M (Q2 2026)BTC held 18,005 → 11,380 (six months)CEO pay $83.5M (2024) → $3.46M (2025)Form 10-K 2025 · 8-Ks Jan 16, Apr 30, Aug 10, 2026 · proxies 2025 and 2026 · Data Center Dynamics Aug 2026 (tenant unconfirmed)
The ledgers. The same company read three ways. The miner is the largest in Texas and still growing its hashrate; the landlord has ten billion dollars of rent under contract and a gigawatt more under letter; the shareholder has paid for both with dilution, losses, and the sale of a third of the treasury in six months. Which ledger the company is running on will be settled at Corsicana.

The honest counterweight: the shareholder's ledger

The third story the filings tell. Riot has reported a net loss in four of its last five years – $509.6 million in 2022, $49.5 million in 2023, $663.2 million in 2025, and $237.2 million in the second quarter of 2026 alone – and its one profitable year, 2024's $109.4 million, came from a new accounting rule that marks bitcoin to market rather than from operations.[10][17][33][39][29] It has paid for its growth with paper: about 84 million shares in 2021 became about 378 million by 2026, four and a half times as many.[38] It paid its chief executive $83,532,328 for 2024, most of it a $75.2 million performance-share grant, against a median employee's $58,875 – 1,419 to one – and cut him to $3.46 million with no long-term grant the next year “in direct response to 2025 Say-on-Pay feedback.”[31][38] And it has sold the asset it exists to accumulate: 18,005 bitcoin at the end of 2025 became 11,380 by June 30, 2026, some 7,000 coins sold in six months to buy the Rockdale land and pour the frontier lab's foundations, with 5,821 of the remainder pledged against a loan.[32][39] Set against it, the miner's case: the largest site on the continent, hashrate up nearly four-fold in three years, power at three cents, ten billion dollars of rent under contract, and a county that said no in March and yes in October.[18][37][26] Two things this page does not say: the Granbury noise litigation is Marathon's, not Riot's, and the Core Scientific shareholders who rejected CoreWeave in October 2025 were not voting on anything of Riot's.[45]

The fair reading is that Riot's Texas decade has been a single bet made three times – on cheap power at Rockdale, on the state paying for flexibility, and now on AI paying for capacity – and that the third bet is the first one whose counterparty is not the Texas grid or the Bitcoin price but a tenant with a twenty-year lease. Whether that makes Riot a better company or a different one, the shareholder who has been diluted four and a half times to fund it will find out at Corsicana.

Where does Riot stand today?

As of September 2026: 700 megawatts developed at Rockdale and 400 at Corsicana, 44.4 exahash, 11,380 bitcoin, 50 megawatts leased to AMD and 191 to a lab no one will name, a 756-megawatt letter of intent it has said converting to a lease is “a priority for the balance of 2026,” a market value near nine billion dollars, and a place in the Governor's audit it has volunteered for.[32][39][37][41] The place it made is on Rockdale, Texas and Bitcoin; the grid that pays it is on ERCOT and Bitcoin; the regulator writing the rules for the load it is becoming is on the Public Utility Commission and Bitcoin. This page is the miner that learned to stop, and what it is building where the mine was.

Frequently asked questions

What is Riot Platforms?

A Castle Rock, Colorado company, listed on Nasdaq as RIOT, that renamed itself from Bioptix to Riot Blockchain in October 2017, became Riot Platforms in January 2023, and is the largest Bitcoin miner in Texas: 700 developed megawatts at Rockdale in Milam County, bought with Whinstone in May 2021, and 400 of a planned 1,000 megawatts at Corsicana in Navarro County, energized in April 2024, plus sites in Kentucky. Jason Les has been chief executive since February 2021 and Benjamin Yi executive chairman since May 2021. It employed 816 people at the end of 2025, about 63% of them in Texas, and ran 44.4 exahash, about 4.6% of the Bitcoin network, in mid-2026.

How much does Riot earn for switching off?

By its own reporting, $6.5 million in power credits in 2021, $27.3 million in 2022, $71.2 million in 2023, $33.7 million in 2024, and $56.7 million in 2025 - 'nearly $10,000 per Bitcoin mined' that year. The credits combine two things: resale of power it has bought at a fixed price under its contract with TXU, and ERCOT's payments for ancillary services and demand response. In August 2023 it booked $31.7 million against 333 bitcoin mined; $24.2 million of that was TXU resale and $7.4 million ERCOT money, which Riot called 'less than one percent of the program.' In 2023 the credits were about 38% of mining revenue; in 2025 about 10%.

What is Riot's AI pivot?

A conversion of its power sites from mining to data-center leasing. In January 2025 it began evaluating about 600 megawatts at Corsicana for AI and high-performance computing and halted the second mining phase there, after pressure from Starboard Value and D. E. Shaw, which then helped seat three directors. In January 2026 it signed AMD for 25 megawatts at Rockdale, expanded to 50 in April, about $636 million over ten years. In April 2026 it signed a non-binding letter of intent for all 756 megawatts of Corsicana's planned capacity with one tenant. On August 10, 2026 it announced a twenty-year, 191-megawatt lease at Rockdale with 'one of the world's leading frontier AI labs,' about $9.1 billion in base rent; Bloomberg identified the tenant as Anthropic, which neither company has confirmed.

What is Riot's record with Texas counties and the Legislature?

Navarro County's commissioners unanimously refused its Corsicana reinvestment zone in March 2024 - 'They created a lot of controversy' - then passed a ten-year abatement 3–2 that October on a pledge of $640 million and 140 jobs; Milam County approved a 75% ten-year abatement for the Rockdale data center in February 2026, 4–1. At the Legislature, Riot's Pierre Rochard testified against Kolkhorst's 2023 mining brake ('Bitcoin miners are the number 1 employer in Rockdale') and for the Strategic Bitcoin Reserve in 2025. With the Texas Blockchain Council it sued the Department of Energy over an emergency survey in February 2024 and won in a week. Its federal lobbying rose from $280,000 in 2022 to $1.16 million in 2024.

Is Riot profitable?

Rarely. Net losses of $509.6 million in 2022, $49.5 million in 2023, and $663.2 million in 2025, and $237.2 million in the second quarter of 2026; the one profitable year, 2024's $109.4 million, came from a new accounting rule that marks bitcoin holdings to market. Shares outstanding rose from about 84 million in 2021 to about 378 million in 2026. Bitcoin held fell from 18,005 at the end of 2025 to 11,380 by June 2026 as the company sold to fund data-center construction. Chief executive pay was $83.5 million in 2024, a ratio of 1,419 to one against the median employee, and $3.46 million in 2025 after shareholders objected.

Sources

Primary record first: the company's own SEC filings – annual reports, current reports, and proxy statements – and its press releases and responses; the Legislature's witness lists; the Navarro County commissioners' resolution; the Governor's releases; then CNBC, the Dallas Morning News, the Corsicana Daily Sun, KXXV, CoinDesk, Data Center Dynamics, and OpenSecrets for the quotes, the votes, and the reporting. Where the identity of a tenant is reported but unconfirmed by either party, the page says so. This is a research and reference article, not financial, investment, or legal advice.

  1. [1]Riot Blockchain - Form 8-K exhibit (October 2017): Bioptix, Inc. renamed Riot Blockchain, Inc.
  2. [2]CNBC - A public company changed its name to Riot Blockchain and its shares rocketed (February 16, 2018): the investigation into the rename, the stock, and the insiders
  3. [3]Riot Blockchain - Form 10-K for 2020: the April 9, 2018 SEC subpoena; the investigation closed January 29, 2020 with no enforcement recommended
  4. [4]CNBC - Riot Blockchain CEO John O'Rourke is out (September 8, 2018): named in the SEC's unrelated $27 million market-manipulation case
  5. [5]Riot Blockchain - Riot announces appointment of Jason Les as CEO (February 8, 2021): "Bitcoin positioned to disrupt the global financial system"
  6. [6]Riot Blockchain - Riot to acquire Whinstone (April 8, 2021): $80 million cash and 11.8 million shares, about $651 million at announcement; 750 MW at Rockdale
  7. [7]Riot Blockchain - Riot completes acquisition of Whinstone US (May 26, 2021): Les - "the most significant milestone in Riot's history"
  8. [8]Riot Blockchain - Riot announces 1 GW development in Navarro County, Texas (April 27, 2022): Corsicana; 265 acres; initial 400 MW; immersion cooling
  9. [9]Dallas Morning News - "We do not want this": Corsicana group protests Riot Blockchain's Bitcoin mining facility (June 16, 2022): Concerned Citizens of Navarro County
  10. [10]Riot Platforms - Riot reports full-year 2022 financial results: revenue $259 million; net loss $509.6 million; power credits $27.3 million
  11. [11]GlobeNewswire - Riot Blockchain announces corporate rebranding to Riot Platforms (January 3, 2023)
  12. [12]Texas Legislature Online - Senate Business and Commerce witness list, March 28, 2023: Pierre Rochard, Riot Platforms, against SB 1751
  13. [13]Bitcoin Magazine - Texas Senate committee hears testimony on Bitcoin mining bill (March 2023): Rochard - "Bitcoin miners are the number 1 employer in Rockdale. Bitcoin miners are also the number 1 taxpayer to Rockdale ISD"
  14. [14]Riot Platforms - Form 8-K exhibit (September 6, 2023): August 2023 - $31.7 million in power and demand-response credits, $24.2 million from power sold under the TXU agreement and $7.4 million from ERCOT demand response, against 333 bitcoin mined; Les - "August was a landmark month"
  15. [15]Riot Platforms - Riot responds to recent inquiries regarding its power strategy (September 8, 2023): the ERCOT share "less than one percent of the program, which administered nearly $1 billion"
  16. [16]Dallas Morning News - Here's what ERCOT paid a Bitcoin miner to curtail electric use this summer (October 5, 2023): about $13 million from ERCOT itself; the rest resale under the retail contract
  17. [17]Riot Platforms - Riot reports full-year 2023 financial results: revenue $281 million; net loss $49.5 million; power credits $71.2 million, about 2,497 bitcoin equivalent; 6,626 bitcoin mined; 12.4 EH/s
  18. [18]Riot Platforms - Form 10-K for 2023: Rockdale expanded to 700 MW, "believed to be the largest single Bitcoin mining facility in North America"; Takata v. Riot dismissed with prejudice August 25, 2023
  19. [19]CoinDesk - Texas Blockchain Council, Riot Platforms sue Department of Energy and OMB over emergency survey (February 23, 2024)
  20. [20]Corsicana Daily Sun - Commissioners deny reinvestment zone, disapprove Bitcoin tax abatements (March 2024): Navarro County unanimous; Commissioner Brewer - "I don't think it's a good investment. They created a lot of controversy"
  21. [21]Riot Platforms - Riot energizes new Corsicana facility in Navarro County (April 18, 2024): the 400 MW substation
  22. [22]Corsicana Daily Sun - Riot reps speak about role in community (May 24, 2024): Schatz - "The only thing that we do as far as water consumption is just topping off our retention pond"
  23. [23]Riot Platforms - Riot proposes to acquire Bitfarms for US$2.30 per share (May 28, 2024): Les - "deeply concerned that the founders on the Bitfarms Board may not be acting in the best interests of all Bitfarms shareholders"
  24. [24]Riot Platforms - Riot announces the acquisition of Block Mining (July 23, 2024): $92.5 million; Kentucky; total potential capacity to 2 gigawatts
  25. [25]Riot Platforms - Bitfarms and Riot announce settlement (September 23, 2024): a board seat; standstill; Riot's stake about 19.9%
  26. [26]Navarro County Commissioners Court - Resolution 2024.13, tax abatement agreement with Riot Corsicana LLC (October 15, 2024, PDF): passed 3–2; ten years; $640 million pledged investment; 140 jobs
  27. [27]Riot Platforms - Form 8-K exhibit (January 21, 2025): formal evaluation of about 600 MW at Corsicana for AI and high-performance computing; Phase II mining halted; hashrate target cut to 38.4 EH/s; Les - "maximizing the potential of our assets"
  28. [28]Riot Platforms - Riot announces changes to its board and update on AI/HPC evaluation (February 13, 2025): three new directors "with constructive, independent input from each of Starboard Value LP and The D. E. Shaw Group"
  29. [29]Riot Platforms - Riot reports full-year 2024 financial results: revenue $376.7 million; net income $109.4 million on the fair-value accounting change; power credits $33.7 million; 4,828 bitcoin mined; 31.5 EH/s; 17,722 bitcoin held
  30. [30]Riot Platforms - Riot closes acquisition of Rhodium assets at Rockdale (April 28, 2025): $185 million; the legacy hosting contracts "generated a gross loss of approximately $15 million" in 2024
  31. [31]Riot Platforms - 2025 proxy statement (June 2025): 2024 total compensation for Jason Les $83,532,328 including a $75.2 million performance-share grant; median employee $58,875; ratio 1,419 to 1
  32. [32]Riot Platforms - Form 10-K for 2025 (March 2026): principal office Castle Rock, Colorado; Rockdale 700 MW developed, Corsicana 400 MW of 1 GW; the TXU power blocks (130, 65, and 150 MW, fixed price, to 2027 and 2030); 816 employees, about 63% in Texas; 38.5 EH/s; 18,005 bitcoin held
  33. [33]Riot Platforms - Riot reports full-year 2025 financial results and strategic highlights (March 2, 2026): revenue $647.4 million; net loss $663.2 million; power credits $56.7 million, "nearly $10,000 per Bitcoin mined"; 5,686 bitcoin mined
  34. [34]Riot Platforms - Form 8-K exhibit (January 16, 2026): the 25 MW AMD lease at Rockdale, ten years plus options, about $311 million; and the purchase of the 200-acre Rockdale site for $96 million, funded by the sale of about 1,080 bitcoin
  35. [35]KXXV - Milam County approves tax abatement for new data center (February 2026): 4–1; 75% for ten years from 2028; Commissioner Payne - "I thought that was too steep"
  36. [36]The Block - Riot, SBI Crypto reach $20 million settlement in Texas Bitcoin mining dispute (2026): the inherited Whinstone hosting claim
  37. [37]Riot Platforms - Form 8-K exhibit, first-quarter 2026 results (April 30, 2026): the second 25 MW AMD phase; a non-binding letter of intent for the full ~756 MW at Corsicana with a single tenant; 15,679 bitcoin held; 42.5 EH/s; all-in power cost 3.0 cents per kWh
  38. [38]Riot Platforms - 2026 proxy statement (June 2026): the board - Yi, Les, D'Ambrosio, Leverton, Mouton, Turner; 2025 compensation for Les about $3.46 million with no long-term grant "in direct response to 2025 Say-on-Pay feedback"; about 378 million shares
  39. [39]Riot Platforms - Form 8-K exhibit, second-quarter 2026 results (August 10, 2026): a 191 MW, twenty-year lease at Rockdale with "one of the world's leading frontier AI labs," about $9.1 billion base, 96 MW by December 2027 and the full 191 MW by June 2028; net loss $237.2 million; 11,380 bitcoin held after selling about 4,300; 44.4 EH/s; Les - "a defining moment in our evolution"
  40. [40]Data Center Dynamics - Riot Platforms agrees 191 MW, 20-year lease with Anthropic worth $9.1 billion, report says (August 2026): Bloomberg's identification; "Riot declined to comment and Anthropic didn't respond"
  41. [41]Office of the Governor - Governor Abbott announces Riot Platforms and Comanche Circle data center commit to comply with his data center standards (August 18, 2026)
  42. [42]Riot Platforms - Support Governor Abbott, an open letter from Jason Les (August 2026): "We support your commonsense principles of ratepayer protection, water stewardship"; $17 million for Navarro County water infrastructure; about 60% of Dawson ISD's tax base
  43. [43]OpenSecrets - Riot Platforms federal lobbying: $280,000 (2022), $470,000 (2023), $1.16 million (2024); Holland & Knight; Brian Morgenstern registered in-house
  44. [44]CryptoSlate - Riot's Pierre Rochard tells Texas Senate a state Bitcoin reserve is needed to prepare for future downturns (February 2025): "now is the perfect time to make a strategic investment"
  45. [45]CNBC - Core Scientific shareholders reject $9 billion CoreWeave offer (October 30, 2025): the deal Riot was not part of