Texas hosts the largest concentration of industrial Bitcoin mining in the United States. The biggest sites are Riot's 700 MW Rockdale facility in Milam County — the largest in North America — Riot's Corsicana campus, MARA's Granbury mine, and Hut 8's 280 MW King Mountain site. Several former Bitcoin mines, led by Galaxy's Helios campus, are now converting to AI data centers.
Key facts
- Riot's Rockdale facility has 700 MW of developed capacity — the largest single Bitcoin mining facility in North America.[1]
- Riot's Corsicana campus has a full gigawatt approved by ERCOT, with 400 MW mining Bitcoin and the remaining 600 MW under AI/HPC evaluation since 2025.[2]
- On July 6, 2026, Galaxy delivered the first 133 MW of its former Helios Bitcoin mine to CoreWeave under a 15-year, 526 MW AI lease.[11]
- MARA bought its Granbury mine in January 2024 as part of a $178.6 million, 390 MW two-site acquisition from Generate Capital.[6]
- In August 2023, ERCOT paid Riot $31.7 million in power credits to curtail mining during the Texas heat wave.[17]
Riot Rockdale (Whinstone)
Rockdale · Milam County · online 2020
700 MW developed · Bitcoin mining
The flagship. Built by Whinstone on the grounds of Alcoa's shuttered aluminum smelter, acquired by Riot in May 2021 for roughly $651 million, and expanded to 700 MW — the largest single Bitcoin mining facility in North America by developed capacity.
What does this map show?
This map tracks the ten most consequential industrial Bitcoin mining sites in Texas — roughly 2.8 GW of developed capacity, and more than 4 GW counting ERCOT-approved expansion. Every capacity figure is the operator's own published number or reputable trade-press reporting, cited below. Smaller and off-grid operations — including the flare-gas miners of the Permian Basin — aren't pinned here, so treat this as the industrial backbone, not a census. The dataset was last verified July 22, 2026, and we re-verify it quarterly alongside the history of Bitcoin in Texas.
Where are the biggest Bitcoin mines in Texas?
The biggest Bitcoin mines in Texas are Riot's Rockdale facility (700 MW developed) and Corsicana campus (400 MW mining, 1 GW approved), MARA's Granbury site (~300 MW), Cipher's Black Pearl (300 MW) and Odessa (207 MW), and Hut 8's King Mountain (280 MW).[1][2][9][12] Rockdale is where the industrial era began: Bitmain broke ground on the former Alcoa aluminum smelter land in 2019, Whinstone built the giant next door, and Riot bought it in May 2021 for roughly $651 million.[3][4] One town in Milam County — hollowed out when the smelter closed — became the mining capital of the Western Hemisphere.
Why is Bitcoin mining concentrated in West Texas?
Because that's where the stranded power is. West Texas generates enormous wind and solar output that transmission lines can't always carry to the cities, and miners are the buyers of last resort for those electrons. Hut 8's King Mountain site sits directly beside a wind farm on a mesa outside McCamey.[12] Layer1 proved the model first: in February 2020 — before Riot, before China's ban — the Peter Thiel-backed startup was mining in liquid-cooled containers off its own 100 MW substation in Ward County, powering down to sell energy back when prices spiked.[15][16] That playbook — mine cheap, curtail high — became standard practice through ERCOT's demand response programs, which pay large loads to power down when the grid is stressed.[17]
Why are Bitcoin mines turning into AI data centers?
Because the scarcest resource in computing is no longer chips — it's connected power, and miners spent a decade accumulating it. Galaxy bought the distressed Argo Helios mine in Dickens County for $65 million in December 2022; on July 6, 2026, it delivered the first 133 MW to CoreWeave under a 15-year lease projected to generate over $1 billion a year at full buildout.[11] Core Scientific is converting its Denton campus in a $6.1 billion buildout.[13][14] Cipher's brand-new Black Pearl site leased straight to Amazon.[10] ERCOT's interconnection queue now holds roughly 226 GW of requests, most of it AI.[19] This is not Bitcoin losing to AI — it's the infrastructure Bitcoin built becoming the on-ramp for the next compute frontier, while mining stays the anchor tenant at sites like Rockdale.
The counterweight: Granbury's noise fight
The record isn't all triumph, and we keep the hard parts in. MARA's Granbury mine runs behind-the-meter at the 1,115 MW Wolf Hollow gas plant, and its cooling fans have made it the most litigated Bitcoin site in Texas: neighbors report sleep disruption and hearing problems, a Hood County constable issued 37 noise citations, and residents have filed nuisance suits in both state and federal court.[7][8] How MARA answers — with sound walls, immersion cooling, or a settlement — will shape how close to homes the next generation of sites gets built.
How to cite this map
This dataset is free to cite with attribution (CC BY 4.0): TexasBitcoin, “Texas Bitcoin Mining Map,” texasbitcoin.com/bitcoin-mining-map-texas, updated July 22, 2026. Corrections and additions are welcome — reach us via the about page. Looking for the people behind the machines? Start with Texas Bitcoin meetups and conferences.
The dataset
All 10 tracked sites, verified July 22, 2026.
Riot Rockdale (Whinstone) · Riot Platforms
Rockdale · Milam County · online 2020
700 MW developed · Bitcoin mining
The flagship. Built by Whinstone on the grounds of Alcoa's shuttered aluminum smelter, acquired by Riot in May 2021 for roughly $651 million, and expanded to 700 MW — the largest single Bitcoin mining facility in North America by developed capacity. [1][3]
Bitdeer Rockdale · Bitdeer
Rockdale · Milam County · online 2019
~170 MW operating (reported) · Bitcoin mining
Next door to Riot on the same former Alcoa land — the campus where Bitmain first broke ground in 2019, making Rockdale the town where industrial-scale Texas mining began. [4][5]
Riot Corsicana · Riot Platforms
Corsicana · Navarro County · online 2024
400 MW mining · 1 GW approved · Mining + AI/HPC pivot underway
Riot's second Texas gigasite, with a full gigawatt approved by ERCOT. 400 MW mines Bitcoin today; in 2025 Riot halted further mining expansion to evaluate AI/HPC uses for the remaining 600 MW. [2]
MARA Granbury · MARA Holdings
Granbury · Hood County · online 2022
~300 MW behind-the-meter · Bitcoin mining
Runs behind-the-meter at the 1,115 MW Wolf Hollow gas plant. MARA bought it in January 2024 in a $178.6 million two-site deal — and its cooling-fan noise made Granbury the center of the state's hardest local fight over mining. [6][7][8][18]
Core Scientific Denton · Core Scientific / CoreWeave
Denton · Denton County · online 2022
~260 MW critical IT (AI conversion) · Converted to AI/HPC
A city-partnered Bitcoin campus that became the template for the AI pivot: a $6.1 billion conversion to high-performance computing for CoreWeave, which then agreed to acquire Core Scientific outright. [13][14]
Cipher Odessa · Cipher Mining
Odessa · Ector County · online 2022
207 MW · Bitcoin mining
Cipher's Permian Basin workhorse — 207 MW in the middle of oil-and-gas country, where drilling rigs and hashboards share the same skyline. [9]
Cipher Black Pearl · Cipher Mining
Wink · Winkler County · online 2025
300 MW · Mining + AI/HPC pivot underway
Came online mining Bitcoin in 2025 and almost immediately became something bigger: the site is now leased to Amazon for AI infrastructure, with mining winding down as GPUs move in. [10]
Galaxy Helios · Galaxy Digital
Dickens County · online 2022
800 MW approved · 133 MW live for AI · Converted to AI/HPC
Built as Argo's flagship mine, bought by Galaxy for $65 million in December 2022 out of Argo's distress, and reborn as an AI campus: on July 6, 2026 Galaxy delivered its first 133 MW to CoreWeave under a 15-year, 526 MW lease. [11]
Hut 8 King Mountain · Hut 8
McCamey · Upton County · online 2022
280 MW · Bitcoin mining
280 MW co-located with the King Mountain wind farm on a West Texas mesa — proof of the Texas thesis that miners are buyers of last resort for renewable power in the middle of nowhere. [12]
Layer1 (historic) · Layer1 Technologies
Ward County · online 2020
100 MW substation (2020) · Historic site
The Peter Thiel-backed pioneer. In February 2020 — before Riot, before the China ban — Layer1 was mining in liquid-cooled containers off its own 100 MW West Texas substation and selling power back to the grid when prices spiked. The playbook everyone else later ran. [15][16]
Frequently asked questions
What is the largest Bitcoin mine in Texas?
Riot's Rockdale facility in Milam County is the largest Bitcoin mine in Texas, with 700 MW of developed capacity — the largest single Bitcoin mining facility in North America. It was built by Whinstone on the site of Alcoa's former aluminum smelter and acquired by Riot in May 2021 for roughly $651 million.
Where are Bitcoin mines located in Texas?
Texas Bitcoin mines cluster in two zones: central Texas industrial towns like Rockdale (Riot, Bitdeer), Corsicana (Riot), Granbury (MARA), and Denton (Core Scientific), and the wind- and gas-rich west — Odessa and Wink (Cipher), McCamey (Hut 8), and Dickens County (Galaxy Helios).
Why are Texas Bitcoin mines becoming AI data centers?
Because miners already hold what AI needs most: hundreds of megawatts of grid-approved power. Galaxy's Helios campus signed a 15-year CoreWeave lease and delivered its first 133 MW in July 2026, Core Scientific is converting Denton in a $6.1 billion buildout, and Cipher leased its new Black Pearl site to Amazon.
Why is so much Bitcoin mining in West Texas?
West Texas has abundant wind and solar generation, cheap land, and transmission that often carries more power than local demand can absorb. Miners act as flexible buyers of that stranded energy — Hut 8's 280 MW King Mountain site sits directly beside a wind farm — and power down when the grid needs the electrons back.
Do Bitcoin mines strain the Texas grid?
Large miners enroll with ERCOT as interruptible load and are paid to shut off during scarcity. In August 2023, Riot earned $31.7 million in power credits for curtailing during the heat wave. The real local friction has been noise, not power: MARA's Granbury mine faces nuisance lawsuits from neighbors over its cooling fans.
Sources
- [1]Riot Platforms — Rockdale facility (700 MW developed)
- [2]Riot Platforms — January 2025 Production and Operations Update (SEC exhibit): Corsicana 400 MW mining, 1 GW approved, AI/HPC evaluation
- [3]Fortune — Inside Whinstone/Riot's Rockdale mine (March 2022)
- [4]CNBC — Bitcoin mining giants Bitdeer, Riot in Rockdale, Texas (October 2021)
- [5]Global Energy Monitor — Bitdeer Rockdale facility profile
- [6]MARA (GlobeNewswire) — Definitive agreement to acquire two mining sites for $178.6M, 390 MW total (December 2023)
- [7]Blockspace — Nine Texas residents sue MARA, expanding Granbury noise fight (2026)
- [8]Earthjustice — Granbury residents sue local Bitcoin mine over noise (October 2024)
- [9]Cipher Mining — business update (SEC exhibit): Odessa 207 MW
- [10]Data Center Dynamics — Cipher launches Black Pearl Bitcoin mining site in Winkler County (2025)
- [11]The Block — Galaxy delivers 133 MW of critical IT load to CoreWeave as Helios turns AI hub (July 2026)
- [12]Cleanview — Hut 8 King Mountain data center, Upton County (280 MW, operational 2022)
- [13]Core Scientific — $1.2B CoreWeave expansion at Denton brings critical IT load to ~260 MW (February 2025)
- [14]CoStar — Core Scientific converts Denton Bitcoin campus to $6.1B data center hub
- [15]The Block — Peter Thiel-backed Layer1 begins mining at its West Texas facility (February 2020)
- [16]Forbes — Why is this Peter Thiel-backed startup mining Bitcoin in West Texas? (February 2020)
- [17]CNBC — Texas paid Riot $31.7 million to shut down during August 2023 heat wave
- [18]Baxtel — MARA Granbury, TX data center profile (~300 MW)
- [19]CoinGeek — ERCOT's large-load interconnection queue reaches ~226 GW, dominated by AI data centers (2026)